Changes in PJM Queue between August 10th, 2021 and November 4th, 2021.
Where an existing project has some updated field, you’ll find two rows for that project, with the new entry on top, updated fields highlighted in green, and deprecated fields highlighted in red in the bottom row.
Fully new queue positions appear as individual rows with all fields highlighted green.
## old_obs new_obs changes additions removals
## 7470 8059 503 589 0
## Truncating HTML diff table to ${limit_html} rows...
## Creating HTML table for first ${limit_html} rows
| QueueNumber | chng_type | Name | CommercialName | State | County | Status | TransmissionOwner | MaximumFacilityOutput | MWEnergy | MWCapacity | MWInService | CapacityorEnergy | ProjectType | Fuel | ProjectACOrDC | RightsMW | InitialStudy | FeasibilityStudy | FeasibilityStudyStatus | SystemImpactStudy | SystemImpactStudyStatus | FacilitiesStudy | FacilitiesStudyStatus | InterimInterconnectionServiceAgreement | InterimInterconnectionServiceAgreementStatus | WholesaleMarketParticipationAgreement | ConstructionServiceAgreement | ConstructionServiceAgreementStatus | UpgradeConstructionServiceAgreement | UpgradeConstructionServiceAgreementStatus | BackfeedDate | QueueDate | LongTermFirmServiceStartDate | LongTermFirmServiceEndDate | TestEnergyDate | WithdrawalDate | WithdrawnRemarks | ProjectedInServiceDate | RevisedInServiceDate | ActualInServiceDate | SuspensionDate | AttachmentType | AlternateQueue | SlideQueue |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| AA1-111 | + | Moshannon-East Towanda 230kV | Renovo Energy Center | PA | Clinton | Suspended | PENELEC | 463 | 463 | 463 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1111_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1111_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1111_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa1_111_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa1_111_csa.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 6/30/2025 | 6/30/2025 | N/A | N | No | This project slid to the next queue | |||||||||
| AA1-111 | - | Moshannon-East Towanda 230kV | PA | Clinton | Active | PENELEC | 463 | 463 | 463 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1111_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1111_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1111_fac.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 10/31/2019 | N/A | N | No | This project slid to the next queue | ||||||||||||||||
| AA1-114 | + | Harwood-East Hazelton #2 69kV | PA | Carbon | Withdrawn | PPL | 60 | 60 | 7.72 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1114_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1114_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1114_fac.pdf | Document Posted | Withdrawn | N/A | N/A | N/A | 10/31/2014 | N/A | N/A | 9/20/2016 | Customer Initiated Withdrawal | 12/30/2017 | N/A | N | No | |||||||||||||
| AA1-114 | - | Harwood-East Hazelton #2 69kV | PA | Carbon | Withdrawn | PPL | 60 | 60 | 7.72 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1114_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1114_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1114_fac.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 9/20/2016 | Customer Initiated Withdrawal | 12/30/2017 | N/A | N | No | |||||||||||||||
| AA1-115 | + | Thirty First Street 115kV | PA | Blair | Withdrawn | PENELEC | 20 | 20 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1115_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1115_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1115_fac.pdf | Document Posted | Withdrawn | N/A | N/A | N/A | 10/31/2014 | N/A | N/A | 11/17/2016 | Customer Initiated Withdrawal | 6/1/2016 | N/A | N | No | |||||||||||||
| AA1-115 | - | Thirty First Street 115kV | PA | Blair | Withdrawn | PENELEC | 20 | 20 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1115_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1115_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1115_fac.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 11/17/2016 | Customer Initiated Withdrawal | 6/1/2016 | N/A | N | No | |||||||||||||||
| AA1-123 | + | Highland-Sammis 345kV | South Field Energy Power Plant | OH | Columbiana | In Service | ATSI | 1152 | 1152 | 1105 | 1152 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1123_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1123_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1123_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa1_123_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa1_123_csa.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 4/1/2021 | 7/29/2021 | 7/29/2021 | 6/14/2021 | N/A | N | No | |||||||
| AA1-123 | - | Highland-Sammis 345kV | South Field Energy Power Plant | OH | Columbiana | Partially in Service - Under Construction | ATSI | 1152 | 1152 | 1105 | 345 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1123_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1123_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1123_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa1_123_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa1_123_csa.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 4/1/2021 | 7/29/2021 | 7/29/2021 | 6/14/2021 | N/A | N | No | |||||||
| AA1-144 | + | East Towanda-Grover 230kV | Gateway Bradford Plant | PA | Bradford | Withdrawn | PENELEC | 163 | 163 | 163 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1144_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1144_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1144_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa1_144_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa1_144_csa.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 4/30/2022 | 10/12/2021 | Customer Milestone Not Met | 11/30/2021 | 11/30/2021 | N/A | N | No | |||||||
| AA1-144 | - | East Towanda-Grover 230kV | Gateway Bradford Plant | PA | Bradford | Engineering and Procurement | PENELEC | 163 | 163 | 163 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa1144_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa1144_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa1144_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa1_144_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa1_144_csa.pdf | Document Posted | N/A | N/A | 10/31/2014 | N/A | N/A | 4/30/2022 | Customer Milestone Not Met | 11/30/2021 | 11/30/2021 | N/A | N | No | ||||||||
| AA2-017 | + | East Palmerton-Acahela 69kV | Penn Forest Wind Project | PA | Carbon | Withdrawn | PPL | 98 | 98 | 12.7 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2017_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2017_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa2017_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa2_017_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa2_017_csa.pdf | Document Posted | N/A | N/A | 11/26/2014 | N/A | N/A | 10/13/2021 | 12/31/2020 | 12/31/2020 | N/A | N | No | |||||||||
| AA2-017 | - | East Palmerton-Acahela 69kV | Penn Forest Wind Project | PA | Carbon | Suspended | PPL | 98 | 98 | 12.7 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2017_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2017_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/aa2017_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/aa2_017_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/aa2_017_csa.pdf | Document Posted | N/A | N/A | 11/26/2014 | N/A | N/A | 12/31/2020 | 12/31/2020 | N/A | N | No | ||||||||||
| AA2-048 | + | Allenwood-Larrabee 34kV | Lakewood-Farmingdale Road Solar Farm & Storage Facility | NJ | Monmouth | Engineering and Procurement | JCPL | 7 | 7 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2048_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2048_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/aa2048_wmpa.pdf | Not Required | N/A | N/A | 2/18/2015 | N/A | N/A | 12/31/2020 | 8/31/2022 | 8/31/2022 | N/A | N | No | |||||||||||
| AA2-048 | - | Allenwood-Larrabee 34kV | Lakewood-Farmingdale Road Solar Farm & Storage Facility | NJ | Monmouth | Engineering and Procurement | JCPL | 7 | 7 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2048_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2048_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/aa2048_wmpa.pdf | Not Required | N/A | N/A | 2/18/2015 | N/A | N/A | 12/31/2020 | 10/1/2021 | 10/1/2021 | N/A | N | No | |||||||||||
| AA2-084 | + | Lappans Road 12.5kV | MD | Washington | Withdrawn | APS | 4 | 4 | 1.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2084_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2084_imp.pdf | Document Posted | Not Required | Withdrawn | N/A | N/A | N/A | 3/31/2015 | N/A | N/A | 9/20/2016 | Customer Initiated Withdrawal | 11/2/2016 | N/A | N | No | ||||||||||||||
| AA2-084 | - | Lappans Road 12.5kV | MD | Washington | Withdrawn | APS | 4 | 4 | 1.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2084_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2084_imp.pdf | Document Posted | Not Required | N/A | N/A | 3/31/2015 | N/A | N/A | 9/20/2016 | Customer Initiated Withdrawal | 11/2/2016 | N/A | N | No | ||||||||||||||||
| AA2-146 | + | Catoctin 34.5kV | MD | Frederick | Withdrawn | APS | 20 | 20 | 10.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2146_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2146_imp.pdf | Document Posted | Not Required | Withdrawn | N/A | N/A | N/A | 4/30/2015 | N/A | N/A | 7/13/2016 | Customer Milestone Not Met | 9/15/2016 | N/A | N | No | ||||||||||||||
| AA2-146 | - | Catoctin 34.5kV | MD | Frederick | Withdrawn | APS | 20 | 20 | 10.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/aa2146_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/aa2146_imp.pdf | Document Posted | Not Required | N/A | N/A | 4/30/2015 | N/A | N/A | 7/13/2016 | Customer Milestone Not Met | 9/15/2016 | N/A | N | No | ||||||||||||||||
| AB1-004 | + | Solar Holler | N/A | N/A | Withdrawn | AEP | 0.4 | 0.4 | 0 | Energy | Generation Interconnection | Solar | Withdrawn | N/A | N/A | 5/4/2015 | N/A | N/A | 5/19/2015 | 10/1/2015 | N/A | Y | No | |||||||||||||||||||||
| AB1-004 | - | Solar Holler, LLC | N/A | N/A | Withdrawn | AEP | 0.4 | 0.4 | 0 | Energy | Generation Interconnection | Solar | Withdrawn | N/A | N/A | 5/4/2015 | N/A | N/A | 5/19/2015 | 10/1/2015 | N/A | Y | No | |||||||||||||||||||||
| AB1-089 | + | Byron-Wayne 345kV #1 | IL | Lee | Active | ComEd | 575 | 575 | 550 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1089_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1089_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1089_fac.pdf | Document Posted | N/A | N/A | 9/30/2015 | N/A | N/A | 6/1/2019 | N/A | N | No | |||||||||||||||||
| AB1-089 | - | Byron-Wayne 345kV #1 | IL | Lee | Active | ComEd | 575 | 575 | 550 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1089_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1089_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2015 | N/A | N/A | 6/1/2019 | N/A | N | No | ||||||||||||||||||
| AB1-092 | + | Moshannon-East Towanda 230kV | Renovo Energy Center | PA | Clinton | Suspended | PENELEC | 504 | 41 | 17 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1092_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1092_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1092_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab1_092_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_092_csa.pdf | Document Posted | N/A | N/A | 9/30/2015 | N/A | N/A | 6/30/2025 | 6/30/2025 | N/A | N | No | ||||||||||
| AB1-092 | - | Moshannon-East Towanda 230kV | PA | Clinton | Active | PENELEC | 504 | 41 | 17 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1092_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1092_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1092_fac.pdf | Document Posted | N/A | N/A | 9/30/2015 | N/A | N/A | 5/1/2019 | N/A | N | No | |||||||||||||||||
| AB1-096 | + | Carroll-Mt. Airy 34.5kV | Union Bridge Solar Facility | MD | Carroll | Engineering and Procurement | APS | 9.9 | 8.2 | 3.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1096_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1096_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab1_096_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_096_csa.pdf | Document Posted | N/A | N/A | 10/7/2015 | N/A | N/A | 1/28/2022 | 11/1/2021 | 11/1/2021 | N/A | N | No | ||||||||||
| AB1-096 | - | Carroll-Mt. Airy 34.5kV | Union Bridge Solar Facility | MD | Carroll | Engineering and Procurement | APS | 9.9 | 8.2 | 3.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1096_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1096_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab1_096_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_096_csa.pdf | Document Posted | N/A | N/A | 10/7/2015 | N/A | N/A | 11/1/2021 | 11/1/2021 | 11/1/2021 | N/A | N | No | ||||||||||
| AB1-109 | + | Mountaineer | Mountaineer #1 | WV | Unknown | Partially in Service - Under Construction | AEP | 1356 | 36 | 36 | 36 | Capacity | Generation Interconnection | Coal | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1109_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1109_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab1_109_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 10/26/2015 | N/A | N/A | 6/1/2021 | 6/1/2021 | 12/31/2018 | N/A | N | No | ||||||||||
| AB1-109 | - | Mountaineer | Mountaineer #1 | WV | Unknown | Under Construction | AEP | 1356 | 36 | 36 | Capacity | Generation Interconnection | Coal | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1109_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1109_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab1_109_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 10/26/2015 | N/A | N/A | 6/1/2021 | 6/1/2021 | N/A | N | No | ||||||||||||
| AB1-173 | + | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 19.8 | 19.8 | 13.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1173_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1173_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1173_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab1_173_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_173_csa.pdf | Document Posted | N/A | N/A | 10/30/2015 | N/A | N/A | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||||
| AB1-173 | - | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 19.8 | 19.8 | 13.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1173_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1173_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1173_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab1_173_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_173_csa.pdf | Document Posted | N/A | N/A | 10/30/2015 | N/A | N/A | 1/1/2022 | 4/1/2022 | 4/1/2022 | N/A | N | No | |||||||||
| AB1-173A | + | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 39.6 | 19.8 | 13.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1173a_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1173a_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1173a_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab1_173a_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_173a_csa.pdf | Document Posted | N/A | N/A | 10/30/2015 | N/A | N/A | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||||
| AB1-173A | - | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 39.6 | 19.8 | 13.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab1173a_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab1173a_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab1173a_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab1_173a_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab1_173a_csa.pdf | Document Posted | N/A | N/A | 10/30/2015 | N/A | N/A | 1/1/2022 | 4/1/2022 | 4/1/2022 | N/A | N | No | |||||||||
| AB2-010 | + | Saltville-Holston 34.5kV - Phase I | Saltville-Holston 34.5kV Solar Facility | VA | Smyth | Withdrawn | AEP | 5 | 5 | 2.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2010_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2010_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2010_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2010_wmpa.pdf | Not Required | N/A | N/A | 12/1/2015 | N/A | N/A | 2/5/2019 | 12/1/2017 | 12/1/2017 | N/A | N | No | ||||||||||
| AB2-010 | - | Saltville-Holston 34.5kV - Phase I | Saltville-Holston 34.5kV Solar Facility | VA | Smyth | Suspended | AEP | 5 | 5 | 2.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2010_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2010_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2010_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2010_wmpa.pdf | Not Required | N/A | N/A | 12/1/2015 | N/A | N/A | 12/1/2017 | 12/1/2017 | N/A | N | No | |||||||||||
| AB2-011 | + | Saltville-Holstone 34.5kV - Phase II | Saltville-Holston 34.5kV Solar Facility | VA | Smyth | Withdrawn | AEP | 5 | 5 | 2.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2011_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2011_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2011_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2011_wmpa.pdf | Not Required | N/A | N/A | 12/1/2015 | N/A | N/A | 2/5/2019 | 12/1/2017 | 12/1/2017 | N/A | N | No | ||||||||||
| AB2-011 | - | Saltville-Holstone 34.5kV - Phase II | Saltville-Holston 34.5kV Solar Facility | VA | Smyth | Suspended | AEP | 5 | 5 | 2.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2011_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2011_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2011_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2011_wmpa.pdf | Not Required | N/A | N/A | 12/1/2015 | N/A | N/A | 12/1/2017 | 12/1/2017 | N/A | N | No | |||||||||||
| AB2-019 | + | Erie West 345kV | PA | N/A | Suspended | PENELEC | 28 | Energy | Merchant Transmission | DC | 28 NFTWR | https://www.pjm.com/pub/planning/project-queues/merch-feas_docs/ab2019_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/merch-impact-studies/ab2019_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/merch-isa/ab2_019_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/merch-csa/ab2_019_csa.pdf | Document Posted | N/A | N/A | 2/3/2016 | N/A | N/A | 3/31/2024 | 3/31/2024 | N/A | S | No | |||||||||||||
| AB2-019 | - | Erie West 345kV | PA | N/A | Engineering and Procurement | PENELEC | 28 | Energy | Merchant Transmission | DC | 28 NFTWR | https://www.pjm.com/pub/planning/project-queues/merch-feas_docs/ab2019_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/merch-impact-studies/ab2019_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/merch-isa/ab2_019_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/merch-csa/ab2_019_csa.pdf | Document Posted | N/A | N/A | 2/3/2016 | N/A | N/A | 3/31/2024 | 3/31/2024 | N/A | S | No | |||||||||||||
| AB2-022 | + | Elizabeth City 34.5kV | Elizabeth City Solar | NC | Camden | Partially in Service - Under Construction | Dominion | 20 | 20 | 13 | 0.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2022_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2022_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2022_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2022_wmpa.pdf | Not Required | N/A | N/A | 2/4/2016 | N/A | N/A | 8/1/2021 | 6/30/2021 | 6/30/2021 | 10/18/2021 | N/A | N | No | ||||||||
| AB2-022 | - | Elizabeth City 34.5kV | Elizabeth City Solar | NC | Camden | Under Construction | Dominion | 20 | 20 | 13 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2022_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2022_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab2022_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ab2022_wmpa.pdf | Not Required | N/A | N/A | 2/4/2016 | N/A | N/A | 8/1/2021 | 6/30/2021 | 6/30/2021 | N/A | N | No | ||||||||||
| AB2-031 | + | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 59.6 | 20 | 13.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2031_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2031_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2031_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_031_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_031_csa.pdf | Document Posted | N/A | N/A | 2/11/2016 | N/A | N/A | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||||
| AB2-031 | - | Brink-Trego 115kV | Meherrin Solar | VA | Greensville | Under Construction | Dominion | 59.6 | 20 | 13.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2031_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2031_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2031_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_031_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_031_csa.pdf | Document Posted | N/A | N/A | 2/11/2016 | N/A | N/A | 1/1/2022 | 4/1/2022 | 4/1/2022 | N/A | N | No | |||||||||
| AB2-037 | + | Keeney-Steele 230kV | Cherrywood Solar I | MD | Caroline | Engineering and Procurement | DPL | 202 | 202 | 76.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2037_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2037_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2037_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_037_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_037_csa.pdf | Document Posted | N/A | N/A | 2/26/2016 | N/A | N/A | 12/1/2023 | 12/1/2023 | N/A | N | No | ||||||||||
| AB2-037 | - | Keeney-Steele 230kV | MD | Caroline | Active | DPL | 202 | 202 | 76.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2037_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2037_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2037_fac.pdf | Document Posted | N/A | N/A | 2/26/2016 | N/A | N/A | 10/31/2019 | N/A | N | No | |||||||||||||||||
| AB2-038 | + | Frostburg 138kV | PA | Somerset | In Service | APS | 139.4 | 0 | 4.2 | 0 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2038_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2038_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab2_038_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_038_csa.pdf | Document Posted | N/A | N/A | 2/29/2016 | N/A | N/A | 12/15/2020 | 12/31/2020 | 12/31/2020 | N/A | N | No | ||||||||||
| AB2-038 | - | Frostburg 138kV | PA | Somerset | In Service | APS | 139.4 | 0 | 4.2 | 0 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2038_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2038_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ab2_038_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_038_csa.pdf | Document Posted | N/A | N/A | 2/29/2016 | N/A | N/A | 12/15/2020 | 10/26/2020 | 12/31/2020 | 12/31/2020 | N/A | N | No | |||||||||
| AB2-067 | + | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1100 | 1100 | 1100 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2067_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2067_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2067_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_067_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_067_csa.pdf | Document Posted | N/A | N/A | 9/23/2021 | 3/31/2016 | N/A | N/A | 6/11/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||
| AB2-067 | - | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1100 | 1100 | 1100 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2067_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2067_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2067_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_067_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_067_csa.pdf | Document Posted | N/A | N/A | 5/8/2021 | 3/31/2016 | N/A | N/A | 3/24/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||
| AB2-092 | + | Bergen 138kV | Bergen Generating Station | NJ | Bergen | Partially in Service - Under Construction | PSEG | 1371.1 | 51.1 | 51.1 | 16 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2092_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2092_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2092_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_092_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 4/26/2016 | N/A | N/A | 12/31/2025 | 12/5/2019 | 12/5/2019 | 12/5/2019 | N/A | N | No | ||||||||
| AB2-092 | - | Bergen 138kV | Bergen Generating Station | NJ | Bergen | Partially in Service - Under Construction | PSEG | 1371.1 | 51.1 | 51.1 | 16 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2092_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2092_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2092_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_092_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 4/26/2016 | N/A | N/A | 12/31/2025 | 12/5/2019 | 12/5/2019 | N/A | N | No | |||||||||
| AB2-093 | + | Ormet 138kV | Hannibal Port Power Project | OH | Monroe | Partially in Service - Under Construction | AEP | 485 | 485 | 485 | 485 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2093_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2093_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2093_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_093_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_093_csa.pdf | Document Posted | N/A | N/A | 12/15/2020 | 4/26/2016 | N/A | N/A | 5/22/2021 | 9/13/2021 | 9/13/2021 | 6/1/2021 | N/A | N | No | ||||||
| AB2-093 | - | Ormet 138kV | Hannibal Port Power Project | OH | Monroe | Under Construction | AEP | 485 | 485 | 485 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2093_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2093_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2093_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_093_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_093_csa.pdf | Document Posted | N/A | N/A | 12/15/2020 | 4/26/2016 | N/A | N/A | 5/22/2021 | 9/13/2021 | 9/13/2021 | N/A | N | No | ||||||||
| AB2-102 | + | Cumberland 230kV | NJ | Cumberland | Active | AEC | 230 | 230 | 225 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2102_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2102_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2102_fac.pdf | Document Posted | N/A | N/A | 4/28/2016 | N/A | N/A | 6/1/2020 | N/A | N | No | |||||||||||||||||
| AB2-102 | - | Cumberland 230kV | NJ | Cumberland | Active | AEC | 230 | 230 | 225 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2102_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2102_imp.pdf | Document Posted | In Progress | N/A | N/A | 4/28/2016 | N/A | N/A | 6/1/2020 | N/A | N | No | ||||||||||||||||||
| AB2-160 | + | Reams 115kV | Reams Solar | VA | Dinwiddie | Engineering and Procurement | Dominion | 80 | 80 | 30.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2160_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2160_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2160_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_160_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_160_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 6/1/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | |||||||||
| AB2-160 | - | Reams 115kV | Reams Solar | VA | Dinwiddie | Engineering and Procurement | Dominion | 80 | 80 | 30.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2160_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2160_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2160_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_160_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_160_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 1/1/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | |||||||||
| AB2-161 | + | Waverly #2 DP 115kV | Waverly Solar | VA | Sussex | Engineering and Procurement | Dominion | 50 | 50 | 19 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2161_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2161_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2161_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_161_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_161_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 9/16/2022 | 9/16/2022 | N/A | N | No | ||||||||||
| AB2-161 | - | Waverly #2 DP 115kV | Waverly Solar | VA | Sussex | Engineering and Procurement | Dominion | 50 | 50 | 19 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2161_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2161_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2161_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_161_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_161_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 1/1/2022 | 9/16/2022 | 9/16/2022 | N/A | N | No | |||||||||
| AB2-170 | + | East Lima-Marysville 345kV | Hardin Energy Center | OH | Hardin | In Service | AEP | 150 | 130 | 49.4 | 130 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2170_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2170_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2170_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_170_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_170_csa.pdf | Document Posted | N/A | N/A | 8/7/2020 | 4/29/2016 | N/A | N/A | 10/13/2020 | 6/1/2021 | 6/1/2021 | 10/13/2020 | N/A | N | No | ||||||
| AB2-170 | - | East Lima-Marysville 345kV | Hardin Energy Center | OH | Hardin | Partially in Service - Under Construction | AEP | 150 | 130 | 49.4 | 130 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2170_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2170_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2170_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_170_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_170_csa.pdf | Document Posted | N/A | N/A | 8/7/2020 | 4/29/2016 | N/A | N/A | 10/13/2020 | 6/1/2021 | 6/1/2021 | 10/13/2020 | N/A | N | No | ||||||
| AC1-001 | + | Delano 138kV | Salt City Solar | OH | Ross | Engineering and Procurement | AEP | 49.9 | 49.9 | 33.93 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1001_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1001_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1001_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_001_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_001_csa.pdf | Document Posted | N/A | N/A | 5/5/2016 | N/A | N/A | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||||
| AC1-001 | - | Delano 138kV | OH | Ross | Active | AEP | 49.9 | 49.9 | 33.93 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1001_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1001_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1001_fac.pdf | Document Posted | N/A | N/A | 5/5/2016 | N/A | N/A | 10/31/2017 | N/A | N | No | |||||||||||||||||
| AC1-044 | + | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1650 | 550 | 550 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1044_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1044_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_044_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_044_csa.pdf | Document Posted | N/A | N/A | 9/23/2021 | 8/31/2016 | N/A | N/A | 3/24/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||
| AC1-044 | - | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1650 | 550 | 550 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1044_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1044_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_044_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_044_csa.pdf | Document Posted | N/A | N/A | 5/8/2021 | 8/31/2016 | N/A | N/A | 3/24/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||
| AC1-054 | + | Kerr Dam–Eatons Ferry 115 kV | Hawtree Creek | NC | Warren | In Service | Dominion | 65 | 65 | 44.5 | 65 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1054_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1054_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1054_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_054_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_054_csa.pdf | Document Posted | N/A | N/A | 8/31/2016 | N/A | N/A | 12/1/2021 | 6/1/2021 | 6/1/2021 | 10/1/2021 | N/A | N | No | |||||||
| AC1-054 | - | Kerr Dam–Eatons Ferry 115 kV | Hawtree Creek | NC | Warren | Under Construction | Dominion | 65 | 65 | 44.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1054_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1054_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1054_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_054_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_054_csa.pdf | Document Posted | N/A | N/A | 8/31/2016 | N/A | N/A | 8/2/2021 | 6/1/2021 | 6/1/2021 | N/A | N | No | |||||||||
| AC1-082 | + | Ravenswood-Hemlock 69kV | OH | Meigs | Active | AEP | 48 | 48 | 29 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1082_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1082_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1082_fac.pdf | Document Posted | N/A | N/A | 9/30/2016 | N/A | N/A | 5/1/2018 | N/A | N | No | |||||||||||||||||
| AC1-082 | - | Ravenswood-Hemlock 69kV | OH | Meigs | Active | AEP | 48 | 48 | 29 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1082_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1082_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2016 | N/A | N/A | 5/1/2018 | N/A | N | No | ||||||||||||||||||
| AC1-083 | + | Smith Mountain-Bearskin 138kV | Maplewood Solar | VA | Pittsylvania | Under Construction | AEP | 100 | 100 | 38 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1083_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1083_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1083_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_083_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_083_csa.pdf | Document Posted | N/A | N/A | 12/15/2021 | 9/30/2016 | N/A | N/A | 12/28/2021 | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||
| AC1-083 | - | Smith Mountain-Bearskin 138kV | Maplewood Solar | VA | Pittsylvania | Under Construction | AEP | 100 | 100 | 38 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1083_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1083_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1083_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_083_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_083_csa.pdf | Document Posted | N/A | N/A | 10/4/2021 | 9/30/2016 | N/A | N/A | 11/1/2021 | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||
| AC1-110 | + | Aurora 138kV | Aurora Generation | IL | Du Page | Engineering and Procurement | ComEd | 1046 | 30 | 30 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1110_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1110_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1110_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_110_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_110_csa.pdf | Document Posted | N/A | N/A | 10/26/2016 | N/A | N/A | 8/28/2023 | 8/28/2023 | N/A | N | No | ||||||||||
| AC1-110 | - | Aurora 138kV | IL | Du Page | Active | ComEd | 1010 | 30 | 30 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1110_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1110_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1110_fac.pdf | Document Posted | N/A | N/A | 10/26/2016 | N/A | N/A | 6/1/2017 | N/A | N | No | |||||||||||||||||
| AC1-117 | + | Stockton 34.5kV | Leatherwood | VA | Henry | Withdrawn | AEP | 20 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1117_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1117_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ac1117_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ac1117_wmpa.pdf | Not Required | N/A | N/A | 10/27/2016 | N/A | N/A | 12/31/2021 | 12/31/2021 | N/A | N | Yes | |||||||||||
| AC1-117 | - | Stockton 34.5kV | Leatherwood | VA | Henry | Suspended | AEP | 20 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1117_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1117_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ac1117_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ac1117_wmpa.pdf | Not Required | N/A | N/A | 10/27/2016 | N/A | N/A | 12/31/2021 | 12/31/2021 | N/A | N | Yes | |||||||||||
| AC1-145 | + | Gretna DP 69 kV | Whitethorn Solar | VA | Pittsylvania | Under Construction | Dominion | 50 | 50 | 19 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1145_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1145_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1145_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_145_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_145_csa.pdf | Document Posted | N/A | N/A | 7/1/2021 | 10/31/2016 | N/A | N/A | 9/1/2021 | 9/1/2021 | 9/1/2021 | N/A | N | No | ||||||||
| AC1-145 | - | Gretna DP 69 kV | Whitethorn Solar | VA | Pittsylvania | Under Construction | Dominion | 50 | 50 | 19 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1145_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1145_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1145_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_145_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_145_csa.pdf | Document Posted | N/A | N/A | 7/1/2021 | 10/31/2016 | N/A | N/A | 7/23/2021 | 9/1/2021 | 9/1/2021 | N/A | N | No | ||||||||
| AC1-158 | + | Spotsylvania 500kV | Spotsylvania Energy Center | VA | Spotsylvania | Partially in Service - Under Construction | Dominion | 500 | 500 | 347.5 | 485 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1158_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1158_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1158_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_158_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_158_csa.pdf | Document Posted | N/A | N/A | 6/1/2020 | 10/31/2016 | N/A | N/A | 8/19/2020 | 12/31/2022 | 12/31/2022 | 9/2/2020 | N/A | N | No | ||||||
| AC1-158 | - | Spotsylvania 500kV | Spotsylvania Energy Center | VA | Spotsylvania | Partially in Service - Under Construction | Dominion | 500 | 500 | 347.5 | 260 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1158_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1158_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1158_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_158_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_158_csa.pdf | Document Posted | N/A | N/A | 6/1/2020 | 10/31/2016 | N/A | N/A | 8/19/2020 | 12/31/2022 | 12/31/2022 | 9/2/2020 | N/A | N | No | ||||||
| AC1-164 | + | Chickahominy 230kV | Keydet Solar Center One | VA | Charles City | Under Construction | Dominion | 320 | 320 | 220.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1164_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1164_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1164_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_164_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_164_csa.pdf | Document Posted | N/A | N/A | 10/1/2021 | 10/31/2016 | N/A | N/A | 10/1/2021 | 6/30/2023 | 6/30/2023 | N/A | N | No | ||||||||
| AC1-164 | - | Chickahominy 230kV | Keydet Solar Center One | VA | Charles City | Engineering and Procurement | Dominion | 320 | 320 | 220.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1164_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1164_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1164_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_164_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_164_csa.pdf | Document Posted | N/A | N/A | 9/1/2021 | 10/31/2016 | N/A | N/A | 10/1/2021 | 6/30/2022 | 6/30/2022 | N/A | N | No | ||||||||
| AC1-174 | + | Losantville 345kV | Riverstart Solar Park | IN | Randolph | Partially in Service - Under Construction | AEP | 100 | 100 | 38 | 66 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1174_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1174_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1174_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_174_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_174_csa.pdf | Document Posted | N/A | N/A | 7/5/2021 | 10/31/2016 | N/A | N/A | 9/24/2021 | 6/1/2022 | 6/1/2022 | 9/24/2021 | N/A | N | No | ||||||
| AC1-174 | - | Losantville 345kV | Riverstart Solar Park | IN | Randolph | Under Construction | AEP | 100 | 100 | 38 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1174_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1174_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1174_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_174_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_174_csa.pdf | Document Posted | N/A | N/A | 7/5/2021 | 10/31/2016 | N/A | N/A | 8/2/2021 | 6/1/2022 | 6/1/2022 | N/A | N | No | ||||||||
| AC1-175 | + | Losantville 345kV | Riverstart Solar Park | IN | Randolph | Partially in Service - Under Construction | AEP | 100 | 100 | 38 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1175_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1175_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1175_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_175_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_175_csa.pdf | Document Posted | N/A | N/A | 7/5/2021 | 10/31/2016 | N/A | N/A | 9/10/2021 | 6/1/2022 | 6/1/2022 | N/A | N | No | ||||||||
| AC1-175 | - | Losantville 345kV | Riverstart Solar Park | IN | Randolph | Under Construction | AEP | 100 | 100 | 38 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1175_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1175_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1175_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_175_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_175_csa.pdf | Document Posted | N/A | N/A | 7/5/2021 | 10/31/2016 | N/A | N/A | 8/2/2021 | 6/1/2022 | 6/1/2022 | N/A | N | No | ||||||||
| AC1-192 | + | Conastone-Peach Bottom | N/A | N/A | Withdrawn | Unknown | Energy | Merchant Transmission | N/A | N/A | 10/31/2016 | N/A | N/A | 11/2/2016 | N/A | EE | No | |||||||||||||||||||||||||||
| AC1-192 | - | Conastone-Peach Bottom | N/A | N/A | Withdrawn | PECO | Energy | Merchant Transmission | N/A | N/A | 10/31/2016 | N/A | N/A | 11/2/2016 | N/A | EE | No | |||||||||||||||||||||||||||
| AC1-204 | + | Elwood | Jackson Generation | IL | Will | Under Construction | ComEd | 1200.9 | 1200.9 | 1115.9 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1204_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1204_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1204_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_204_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_204_csa.pdf | Document Posted | N/A | N/A | 10/31/2016 | N/A | N/A | 11/8/2021 | 11/8/2021 | 11/8/2021 | N/A | N | No | |||||||||
| AC1-204 | - | Elwood | Jackson Generation | IL | Will | Under Construction | ComEd | 1200.9 | 1200.9 | 1115.9 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1204_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1204_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1204_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_204_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_204_csa.pdf | Document Posted | N/A | N/A | 10/31/2016 | N/A | N/A | 11/1/2021 | 11/2/2021 | 11/2/2021 | N/A | N | No | |||||||||
| AC2-050 | + | Tabernacle 12kV | NJ | Burlington | Active | AEC | 10 | 10 | 3.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2050_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2050_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2050_fac.pdf | Document Posted | Not Required | N/A | N/A | 2/10/2017 | N/A | N/A | 6/1/2019 | N/A | N | No | ||||||||||||||||
| AC2-050 | - | Tabernacle 12kV | NJ | Burlington | Active | AEC | 10 | 10 | 3.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2050_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2050_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/10/2017 | N/A | N/A | 6/1/2019 | N/A | N | No | ||||||||||||||||||
| AC2-059 | + | Biers Run-Circleville 138kV | Yellowbud Solar | OH | Ross | Engineering and Procurement | AEP | 127 | 127 | 62.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2059_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2059_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac2_059_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac2_059_csa.pdf | Document Posted | N/A | N/A | 5/1/2022 | 2/16/2017 | N/A | N/A | 6/1/2022 | 12/15/2022 | 12/15/2022 | N/A | N | No | ||||||||
| AC2-059 | - | Biers Run-Circleville 138kV | OH | Ross | Active | AEP | 127 | 127 | 62.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2059_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2059_fac.pdf | Document Posted | N/A | N/A | 2/16/2017 | N/A | N/A | 12/31/2019 | N/A | N | No | |||||||||||||||||
| AC2-120 | + | Ripley 69kV | Ripley Solar | MD | Charles | Engineering and Procurement | SMECO | 27.5 | 27.5 | 10.45 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2120_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2120_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2120_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ac2120_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ac2120_wmpa.pdf | Not Required | N/A | N/A | 3/23/2017 | N/A | N/A | 10/1/2020 | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||
| AC2-120 | - | Ripley 69kV | Ripley Solar | MD | Charles | Engineering and Procurement | SMECO | 27.5 | 27.5 | 10.45 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2120_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2120_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2120_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ac2120_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ac2120_wmpa.pdf | Not Required | N/A | N/A | 3/23/2017 | N/A | N/A | 10/1/2020 | 6/1/2021 | 6/1/2021 | N/A | N | No | |||||||||
| AC2-195 | + | Galion-Roberts South 138kV | Marion County Solar Project | OH | Marion | Engineering and Procurement | ATSI | 100 | 99.96 | 62.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2195_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2195_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2195_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac2_195_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac2_195_csa.pdf | Document Posted | N/A | N/A | 3/31/2017 | N/A | N/A | 10/1/2023 | 10/1/2023 | N/A | N | No | ||||||||||
| AC2-195 | - | Galion-Roberts South 138kV | OH | Marion | Active | ATSI | 100 | 99.96 | 62.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2195_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2195_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2195_fac.pdf | Document Posted | N/A | N/A | 3/31/2017 | N/A | N/A | 12/31/2020 | N/A | N | No | |||||||||||||||||
| AD1-015 | + | Frazeysburg 138 kV | Muskingum Solar | OH | Muskingum | Engineering and Procurement | AEP | 150 | 150 | 57 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1015_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1015_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1015_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_015_isa.pdf | Document Posted | N/A | N/A | N/A | 4/21/2017 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||||
| AD1-015 | - | Frazeysburg 138 kV | OH | Muskingum | Active | AEP | 150 | 150 | 57 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1015_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1015_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1015_fac.pdf | Document Posted | N/A | N/A | 4/21/2017 | N/A | N/A | 6/1/2019 | N/A | N | No | |||||||||||||||||
| AD1-017 | + | Smith Mountain-Bearskin 138 kV | Maplewood Solar | VA | Pittsylvania | Under Construction | AEP | 120 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1017_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1017_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1017_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_017_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_017_csa.pdf | Document Posted | N/A | N/A | 12/17/2021 | 5/11/2017 | N/A | N/A | 12/28/2021 | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||
| AD1-017 | - | Smith Mountain-Bearskin 138 kV | Maplewood Solar | VA | Pittsylvania | Under Construction | AEP | 120 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1017_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1017_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1017_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_017_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_017_csa.pdf | Document Posted | N/A | N/A | 5/11/2017 | N/A | N/A | 4/1/2022 | 4/1/2022 | N/A | N | No | ||||||||||
| AD1-031 | + | Kewanee - E.D. Edwards 138 kV | IL | Henry | Active | ComEd | 70 | 70 | 26.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1031_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1031_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/24/2017 | N/A | N/A | 10/31/2021 | 10/31/2021 | N/A | N | No | |||||||||||||||||
| AD1-031 | - | Kewanee 138 kV | IL | Henry | Active | ComEd | 70 | 70 | 26.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1031_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/24/2017 | N/A | N/A | 10/31/2021 | 10/31/2021 | N/A | N | No | |||||||||||||||||||
| AD1-033 | + | Fentress-Landstown 230 kV | Bedford Solar Center | VA | City of Chesapeake | Partially in Service - Under Construction | Dominion | 70 | 70 | 42 | 14 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1033_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1033_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1033_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_033_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_033_csa.pdf | Document Posted | N/A | N/A | 7/26/2017 | N/A | N/A | 12/31/2021 | 12/1/2021 | 12/1/2021 | 9/17/2021 | N/A | N | No | |||||||
| AD1-033 | - | Fentress-Landstown 230 kV | Bedford Solar Center | VA | City of Chesapeake | Under Construction | Dominion | 70 | 70 | 42 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1033_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1033_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1033_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_033_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_033_csa.pdf | Document Posted | N/A | N/A | 7/26/2017 | N/A | N/A | 8/24/2021 | 12/1/2021 | 12/1/2021 | N/A | N | No | |||||||||
| AD1-039 | + | Kendall-Tazewell & Dresden-Mole Creek | IL | Grundy | Active | ComEd | 1262.7 | 102.7 | 93 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1039_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1039_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/28/2017 | N/A | N/A | 3/1/2022 | 3/1/2022 | N/A | N | No | This project slid to the next queue | ||||||||||||||||
| AD1-039 | - | Kendall-Tazewell & Dresden-Mole Creek | IL | Grundy | Active | ComEd | 1262.7 | 102.7 | 112.7 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1039_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1039_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/28/2017 | N/A | N/A | 3/1/2022 | 3/1/2022 | N/A | N | No | |||||||||||||||||
| AD1-060 | + | Mercersburg-Milnor 34.5 kV | Upton Solar | PA | Franklin | In Service | APS | 15 | 15 | 5.7 | 15 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1060_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1060_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ad1_060_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_060_csa.pdf | Document Posted | N/A | N/A | 8/18/2017 | N/A | N/A | 9/1/2021 | 9/1/2021 | 9/1/2021 | 12/17/2020 | N/A | N | No | ||||||||
| AD1-060 | - | Mercersburg-Milnor 34 kV | Upton Solar | PA | Franklin | In Service | APS | 15 | 15 | 5.7 | 15 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1060_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1060_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ad1_060_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_060_csa.pdf | Document Posted | N/A | N/A | 8/18/2017 | N/A | N/A | 9/1/2021 | 9/1/2021 | 9/1/2021 | 12/17/2020 | N/A | N | No | ||||||||
| AD1-061 | + | McConnelsburg-Mercersburg 34 kV | PA | Franklin | Under Construction | APS | 20 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1061_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1061_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1061_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_061_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_061_csa.pdf | Document Posted | N/A | N/A | 8/18/2017 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||
| AD1-061 | - | McConnelsburg-Mercersburg 34 kV | PA | Franklin | Active | APS | 20 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1061_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1061_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1061_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_061_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_061_csa.pdf | Document Posted | N/A | N/A | 8/18/2017 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||
| AD1-072 | + | Biers Run-Circleville 138 kV | Yellowbud Solar | OH | Ross | Engineering and Procurement | AEP | 147 | 20 | 13.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1072_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1072_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1072_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_072_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_072_csa.pdf | Document Posted | N/A | N/A | 8/31/2017 | N/A | N/A | 12/15/2022 | 12/15/2022 | N/A | N | No | ||||||||||
| AD1-072 | - | Biers Run-Circleville 138 kV | OH | Ross | Active | AEP | 147 | 20 | 13.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1072_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1072_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1072_fac.pdf | Document Posted | N/A | N/A | 8/31/2017 | N/A | N/A | 6/1/2020 | N/A | N | No | |||||||||||||||||
| AD1-081 | + | Beatty-London 138 kV | OH | Madison | Active | ATSI | 196 | 20 | 13.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1081_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1081_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1081_fac.pdf | Document Posted | N/A | N/A | 9/5/2017 | N/A | N/A | 6/1/2020 | N/A | N | No | |||||||||||||||||
| AD1-081 | - | Beatty-London 138 kV | OH | Madison | Active | ATSI | 196 | 20 | 13.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1081_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1081_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/5/2017 | N/A | N/A | 6/1/2020 | N/A | N | No | ||||||||||||||||||
| AD1-083 | + | Page-Bethel 138 kV | Cape Solar | VA | Page | Engineering and Procurement | APS | 100 | 100 | 60.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1083_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1083_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1083_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_083_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_083_csa.pdf | Document Posted | N/A | N/A | 9/11/2017 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||
| AD1-083 | - | Page-Bethel 138 kV | VA | Page | Active | APS | 100 | 100 | 60.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1083_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1083_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1083_fac.pdf | Document Posted | N/A | N/A | 9/11/2017 | N/A | N/A | 12/31/2019 | N/A | N | No | |||||||||||||||||
| AD1-086 | + | E. Frankfort-Goodings Grove | N/A | N/A | Withdrawn | Unknown | Energy | Merchant Transmission | https://www.pjm.com/pub/planning/project-queues/arr-impact-studies/ad1086_arr-imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/arr-facilities-studies/ad1086_arr-fac.pdf | Document Posted | N/A | N/A | 9/14/2017 | N/A | N/A | 8/23/2021 | 6/20/2021 | 6/20/2021 | N/A | EE | No | |||||||||||||||||||||
| AD1-086 | - | E. Frankfort-Goodings Grove | IL | Will | Active | ComEd | 23.9 | Energy | Merchant Transmission | https://www.pjm.com/pub/planning/project-queues/arr-impact-studies/ad1086_arr-imp.pdf | Document Posted | In Progress | N/A | N/A | 9/14/2017 | N/A | N/A | 6/20/2021 | 6/20/2021 | N/A | EE | No | ||||||||||||||||||||||
| AD1-140 | + | Greene-Clark 138 kV | Kingwood Solar | OH | Greene | Engineering and Procurement | ATSI | 175 | 175 | 95.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1140_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1140_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1140_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_140_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_140_csa.pdf | Document Posted | N/A | N/A | 9/29/2017 | N/A | N/A | 9/30/2023 | 9/30/2023 | N/A | N | No | ||||||||||
| AD1-140 | - | Greene-Clark 138 kV | OH | Greene | Active | ATSI | 175 | 175 | 95.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1140_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1140_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1140_fac.pdf | Document Posted | N/A | N/A | 9/29/2017 | N/A | N/A | 5/29/2020 | N/A | N | No | |||||||||||||||||
| AD1-152 | + | Clover-Sedge Hill 230 kV | VA | Halifax | Active | Dominion | 80 | 80 | 48 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1152_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1152_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/ad1_152_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/30/2017 | N/A | N/A | 12/31/2020 | N/A | N | No | |||||||||||||||
| AD1-152 | - | Clover-Sedge Hill 230 kV | VA | Halifax | Active | Dominion | 80 | 80 | 48 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1152_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1152_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2017 | N/A | N/A | 12/31/2020 | N/A | N | No | ||||||||||||||||||
| AD1-155 | + | Meadow Brook-Strasburg 138 kV | Foxglove Solar | VA | Frederick | Engineering and Procurement | APS | 75 | 75 | 37.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1155_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1155_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1155_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_155_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_155_csa.pdf | Document Posted | N/A | N/A | 9/30/2017 | N/A | N/A | 10/31/2023 | 10/31/2023 | N/A | N | No | ||||||||||
| AD1-155 | - | Meadow Brook-Strasburg 138 kV | VA | Frederick | Active | APS | 75 | 75 | 37.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1155_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1155_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1155_fac.pdf | Document Posted | N/A | N/A | 9/30/2017 | N/A | N/A | 12/31/2020 | N/A | N | No | |||||||||||||||||
| AD2-009 | + | McConnellsburg 138 kV | Great Cover Solar LLC | PA | Fulton | Engineering and Procurement | APS | 70 | 70 | 48.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2009_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2009_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2009_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_009_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_009_csa.pdf | Document Posted | N/A | N/A | 11/3/2017 | N/A | N/A | 3/31/2023 | 3/31/2023 | N/A | N | No | ||||||||||
| AD2-009 | - | McConnellsburg 138 kV | PA | Fulton | Active | APS | 70 | 70 | 48.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2009_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2009_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2009_fac.pdf | Document Posted | N/A | N/A | 11/3/2017 | N/A | N/A | 6/30/2019 | N/A | N | No | |||||||||||||||||
| AD2-014 | + | Steubenville 69 kV | OH | Jefferson | Active | AEP | 49.5 | 49.5 | 20.79 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2014_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2014_imp.pdf | Document Posted | In Progress | N/A | N/A | 11/8/2017 | N/A | N/A | 12/31/2019 | N/A | N | No | ||||||||||||||||||
| AD2-014 | - | Steubenville 69 kV | OH | Jefferson | Active | AEP | 53.3 | 53.325 | 22.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2014_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2014_imp.pdf | Document Posted | In Progress | N/A | N/A | 11/7/2017 | N/A | N/A | 12/31/2019 | N/A | N | No | ||||||||||||||||||
| AD2-016 | + | Biers Run-Circleville 138 kV | Yellowbud Solar | OH | Ross | Engineering and Procurement | AEP | 274 | 127 | 62.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2016_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2016_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2016_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_016_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_016_csa.pdf | Document Posted | N/A | N/A | 11/15/2017 | N/A | N/A | 12/15/2022 | 12/15/2022 | N/A | N | No | ||||||||||
| AD2-016 | - | Biers Run-Circleville 138 kV | OH | Ross | Active | AEP | 274 | 127 | 62.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2016_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2016_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2016_fac.pdf | Document Posted | N/A | N/A | 11/15/2017 | N/A | N/A | 12/31/2020 | N/A | N | No | |||||||||||||||||
| AD2-048 | + | Cynthia-Headquarters 69 kV | KY | Harrison | Active | EKPC | 70 | 70 | 46.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2048_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2048_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2048_fac.pdf | Document Posted | N/A | N/A | 1/31/2018 | N/A | N/A | 6/1/2020 | N/A | N | No | |||||||||||||||||
| AD2-048 | - | Cynthia-Headquarters 69 kV | KY | Harrison | Active | EKPC | 70 | 70 | 46.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2048_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2048_imp.pdf | Document Posted | In Progress | N/A | N/A | 1/31/2018 | N/A | N/A | 6/1/2020 | N/A | N | No | ||||||||||||||||||
| AD2-055 | + | Moshannon-East Towanda 230 kV | Renovo Energy Center | PA | Clinton | Suspended | PENELEC | 548 | 44 | 35 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2055_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2055_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2055_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_055_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_055_csa.pdf | Document Posted | N/A | N/A | 2/9/2018 | N/A | N/A | 6/30/2025 | 6/30/2025 | N/A | N | No | ||||||||||
| AD2-055 | - | Moshannon-East Towanda 230 kV | PA | Clinton | Active | PENELEC | 548 | 44 | 35 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2055_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2055_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2055_fac.pdf | Document Posted | N/A | N/A | 2/9/2018 | N/A | N/A | 10/1/2020 | N/A | N | No | |||||||||||||||||
| AD2-059 | + | Chapel Street 138 kV | DE | New Castle | Active | DPL | 0.8 | 0.77 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2059_imp.pdf | Document Posted | Not Required | N/A | N/A | 2/21/2018 | N/A | N/A | 10/1/2018 | N/A | N | No | ||||||||||||||||||
| AD2-059 | - | Chapel Street 138 kV | DE | New Castle | Active | DPL | 0.8 | 0.77 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2059_imp.pdf | Document Posted | N/A | N/A | 2/21/2018 | N/A | N/A | 10/1/2018 | N/A | N | No | |||||||||||||||||||
| AD2-065 | + | Atco 12 kV | Kettle Run | NJ | Burlington | Under Construction | AEC | 2.6 | 2.57 | 1.08 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2065_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2065_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2065_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ad2065_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ad2065_wmpa.pdf | Not Required | N/A | N/A | 2/27/2018 | N/A | N/A | 5/20/2022 | 5/20/2022 | N/A | N | No | ||||||||||
| AD2-065 | - | Atco 12 kV | Kettle Run | NJ | Burlington | Engineering and Procurement | AEC | 2.6 | 2.57 | 1.08 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2065_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2065_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2065_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ad2065_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ad2065_wmpa.pdf | Not Required | N/A | N/A | 2/27/2018 | N/A | N/A | 5/20/2022 | 5/20/2022 | N/A | N | No | ||||||||||
| AD2-066 | + | Mazon-Crescent Ridge 138 kV | IL | Grundy | Active | ComEd | 116 | 116 | 69.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2066_fea.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2018 | N/A | N/A | 9/1/2020 | N/A | N | No | ||||||||||||||||||||
| AD2-066 | - | Mazon-Crescent Ridge | IL | Grundy | Active | ComEd | 116 | 116 | 69.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2066_fea.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2018 | N/A | N/A | 9/1/2020 | N/A | N | No | ||||||||||||||||||||
| AD2-093 | + | Marysville 345kV | OH | Union | Active | AEP | 225 | 225 | 135 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2093_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2093_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2093_fac.pdf | Document Posted | N/A | N/A | 3/20/2018 | N/A | N/A | 12/31/2020 | N/A | N | No | |||||||||||||||||
| AD2-093 | - | Marysville 345kV | OH | Union | Active | AEP | 225 | 225 | 135 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2093_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2093_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/20/2018 | N/A | N/A | 12/31/2020 | N/A | N | No | ||||||||||||||||||
| AD2-100 | + | Kincaid-Pana 345 kV | IL | Christian | Active | ComEd | 210 | 210 | 126 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2100_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/21/2018 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AD2-100 | - | Kincaid-Pana | IL | Christian | Active | ComEd | 210 | 210 | 126 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2100_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/21/2018 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AD2-103 | + | Crane CT 1 115kV | MD | Baltimore County | Withdrawn | BGE | 14 | 14 | 14 | Capacity | Generation Interconnection | Oil | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2103_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2103_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2103_fac.pdf | Document Posted | Withdrawn | N/A | Withdrawn | N/A | N/A | 3/22/2018 | N/A | N/A | 10/27/2021 | 10/31/2019 | N/A | N | No | |||||||||||||
| AD2-103 | - | Crane CT 1 115kV | MD | Baltimore County | Active | BGE | 14 | 14 | 14 | Capacity | Generation Interconnection | Oil | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2103_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2103_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2103_fac.pdf | Document Posted | N/A | N/A | 3/22/2018 | N/A | N/A | 10/31/2019 | N/A | N | No | |||||||||||||||||
| AD2-104 | + | Crane CT 2-3-4 115kV | MD | Baltimore County | Active | BGE | 144.6 | 144.6 | 144.6 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2104_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2104_fac.pdf | Document Posted | Withdrawn | N/A | Withdrawn | N/A | N/A | 3/22/2018 | N/A | N/A | 10/31/2019 | N/A | N | No | ||||||||||||||
| AD2-104 | - | Crane CT 2-3-4 115kV | MD | Baltimore County | Active | BGE | 144.6 | 144.6 | 144.6 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2104_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2104_fac.pdf | Document Posted | N/A | N/A | 3/22/2018 | N/A | N/A | 10/31/2019 | N/A | N | No | |||||||||||||||||
| AD2-163 | + | Broadview-Tangy 138 kV | Madison Fields Solar Project | OH | Madison | Engineering and Procurement | ATSI | 180 | 180 | 120.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2163_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2163_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2163_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_163_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_163_csa.pdf | Document Posted | N/A | N/A | 3/26/2018 | N/A | N/A | 10/1/2023 | 10/1/2023 | N/A | N | No | ||||||||||
| AD2-163 | - | Broadview-Tangy 138 kV | OH | Madison | Active | ATSI | 180 | 180 | 120.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2163_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2163_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2163_fac.pdf | Document Posted | N/A | N/A | 3/26/2018 | N/A | N/A | 12/1/2021 | N/A | N | No | |||||||||||||||||
| AD2-172 | + | Lena 138kV | High Point Solar | IL | Stephenson | Engineering and Procurement | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2172_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2172_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2172_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_172_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_172_csa.pdf | Document Posted | N/A | N/A | 3/28/2018 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | ||||||||||
| AD2-172 | - | Lena 138kV | IL | Stephenson | Active | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2172_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2172_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2172_fac.pdf | Document Posted | N/A | N/A | 3/28/2018 | N/A | N/A | 5/19/2020 | N/A | N | No | |||||||||||||||||
| AD2-180 | + | Elk Garden-Parr Run 138kV | Black Rock Wind | WV | Mineral | Partially in Service - Under Construction | APS | 110 | 110 | 15.08 | 10 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2180_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2180_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2180_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_180_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_180_csa.pdf | Document Posted | N/A | N/A | 3/29/2018 | N/A | N/A | 12/15/2021 | 12/15/2021 | 10/25/2021 | N/A | N | No | ||||||||
| AD2-180 | - | Elk Garden-Parr Run 138kV | Black Rock Wind | WV | Mineral | Under Construction | APS | 110 | 110 | 15.08 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2180_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2180_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2180_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_180_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_180_csa.pdf | Document Posted | N/A | N/A | 3/29/2018 | N/A | N/A | 12/15/2021 | 12/15/2021 | N/A | N | No | ||||||||||
| AD2-189 | + | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1875 | 225 | 186 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2189_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2189_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ad2_189_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_189_csa.pdf | Document Posted | N/A | N/A | 9/23/2021 | 3/30/2018 | N/A | N/A | 6/11/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | |||||||||
| AD2-189 | - | Kammer-Vassell 765kV | Guernsey Power Station | OH | Guernsey | Under Construction | AEP | 1875 | 225 | 186 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2189_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2189_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ad2_189_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_189_csa.pdf | Document Posted | N/A | N/A | 5/8/2021 | 3/30/2018 | N/A | N/A | 3/24/2022 | 12/31/2022 | 12/31/2022 | N/A | N | No | |||||||||
| AD2-213 | + | East Flemington-Lebanon 34.5 kV | VESI - East Flemington Energy Storage | NJ | Hunterdon | Engineering and Procurement | JCPL | 20 | 20 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2213_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2213_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2213_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_213_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_213_csa.pdf | Document Posted | N/A | N/A | 3/30/2018 | N/A | N/A | 8/30/2022 | 8/30/2022 | N/A | N | No | ||||||||||
| AD2-213 | - | East Flemington-Lebanon 34.5 kV | VESI - East Flemington Energy Storage | NJ | Hunterdon | Engineering and Procurement | JCPL | 20 | 20 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2213_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2213_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2213_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_213_isa.pdf | Document Posted | N/A | N/A | N/A | 3/30/2018 | N/A | N/A | 8/30/2022 | 8/30/2022 | N/A | N | No | ||||||||||||
| AE1-007 | + | Camden-Crystal III 69 kV | OH | Preble | Withdrawn | Dayton | 89.9 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1007_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1007_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1007_fac.pdf | Document Posted | Withdrawn | N/A | Withdrawn | N/A | N/A | 4/23/2018 | N/A | N/A | 8/16/2021 | 7/1/2019 | N/A | N | No | |||||||||||||
| AE1-007 | - | Camden-Crystal III 69 kV | OH | Preble | Active | Dayton | 89.9 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1007_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1007_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1007_fac.pdf | Document Posted | N/A | N/A | 4/23/2018 | N/A | N/A | 7/1/2019 | N/A | N | No | |||||||||||||||||
| AE1-032 4948568 | + | AMIL-PJM | N/A | N/A | Withdrawn | Calpine Energy Services, L.P. | 180 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4954950_ltf1.pdf | Withdrawn | N/A | N/A | 5/24/2018 | 6/1/2021 | 6/1/2026 | 10/4/2018 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-032 4948568 | - | AMIL-PJM | N/A | N/A | Withdrawn | 180 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4954950_ltf1.pdf | Withdrawn | N/A | N/A | 5/24/2018 | 6/1/2021 | 6/1/2026 | 10/4/2018 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-033 4950965 | + | ALTE-PJM | N/A | N/A | Withdrawn | Calpine Energy Services, L.P. | 165 | Energy | Long-Term Firm Transmission | Withdrawn | N/A | N/A | 6/4/2018 | 6/1/2022 | 6/1/2027 | 12/21/2018 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-033 4950965 | - | ALTE-PJM | N/A | N/A | Withdrawn | 165 | Energy | Long-Term Firm Transmission | Withdrawn | N/A | N/A | 6/4/2018 | 6/1/2022 | 6/1/2027 | 12/21/2018 | N/A | PP | No | ||||||||||||||||||||||||||
| AE1-042 4954950 | + | TVA-PJM | N/A | N/A | Withdrawn | Calpine Energy Services, L.P. | 180 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1042_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 6/26/2018 | 6/1/2021 | 6/1/2026 | 2/1/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-042 4954950 | - | TVA-PJM | N/A | N/A | Withdrawn | 180 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1042_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 6/26/2018 | 6/1/2021 | 6/1/2026 | 2/1/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-044 | + | Morrisville 230 kV | VA | Fauquier | Active | Dominion | 200 | 200 | 111.7933 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1044_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1044_fac.pdf | Document Posted | N/A | N/A | 7/5/2018 | N/A | N/A | 11/2/2020 | N/A | N | No | |||||||||||||||||
| AE1-044 | - | Morrisville 230 kV | VA | Fauquier | Active | Dominion | 200 | 200 | 111.7933 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1044_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/5/2018 | N/A | N/A | 11/2/2020 | N/A | N | No | ||||||||||||||||||
| AE1-071 | + | Shade Gap-Roxbury 115 kV | PA | Franklin | Active | PENELEC | 100.1 | 100.1 | 62.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1071_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1071_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1071_fac.pdf | Document Posted | N/A | N/A | 7/31/2018 | N/A | N/A | 12/1/2021 | N/A | N | No | |||||||||||||||||
| AE1-071 | - | Shade Gap-Roxbury 115 kV | PA | Franklin | Active | PENELEC | 100.1 | 100.1 | 62.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1071_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1071_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2018 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||
| AE1-095 4966859 | + | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1095_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2020 | 6/1/2021 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-095 4966859 | - | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1095_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2020 | 6/1/2021 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-096 4966862 | + | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1096_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2021 | 6/1/2022 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-096 4966862 | - | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1096_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2021 | 6/1/2022 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-097 4966877 | + | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1097_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2022 | 6/1/2027 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-097 4966877 | - | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1097_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2022 | 6/1/2027 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-100 | + | Axton 138 kV | VA | Henry | Active | AEP | 66 | 66 | 41.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1100_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1100_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1100_fac.pdf | Document Posted | N/A | N/A | 8/31/2018 | N/A | N/A | 12/15/2021 | N/A | N | No | |||||||||||||||||
| AE1-100 | - | Axton 138 kV | VA | Henry | Active | AEP | 66 | 66 | 41.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1100_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1100_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2018 | N/A | N/A | 12/15/2021 | N/A | N | No | ||||||||||||||||||
| AE1-101 | + | McConnellsburg-Texas Eastern 138 kV | Great Cove Solar II | PA | Franklin | Engineering and Procurement | APS | 150 | 150 | 100.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1101_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1101_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1101_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_101_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_101_csa.pdf | Document Posted | N/A | N/A | 8/31/2018 | N/A | N/A | 3/31/2023 | 3/31/2023 | N/A | N | No | ||||||||||
| AE1-101 | - | McConnellsburg-Texas Eastern 138 kV | PA | Franklin | Active | APS | 150 | 150 | 100.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1101_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1101_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1101_fac.pdf | Document Posted | N/A | N/A | 8/31/2018 | N/A | N/A | 5/31/2021 | N/A | N | No | |||||||||||||||||
| AE1-104 | + | BL England 138 kV | Ocean Wind LLC | NJ | Cape May | Engineering and Procurement | AEC | 432 | 432 | 121.4 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1104_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1104_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_104_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_104_csa.pdf | Document Posted | N/A | N/A | 9/6/2018 | N/A | N/A | 10/1/2024 | 10/1/2024 | N/A | N | No | ||||||||||
| AE1-104 | - | BL England 138 kV | NJ | Cape May | Active | AEC | 432 | 432 | 121.4 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1104_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1104_fac.pdf | Document Posted | N/A | N/A | 9/6/2018 | N/A | N/A | 6/1/2023 | N/A | N | No | |||||||||||||||||
| AE1-110 4966477 | + | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966477_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1110_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2030 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE1-110 4966477 | - | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966477_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1110_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2030 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-111 4966479 | + | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966479_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1111_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2031 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE1-111 4966479 | - | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966479_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1111_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2031 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-112 4966484 | + | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966484_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1112_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2032 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE1-112 4966484 | - | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966484_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/ae1112_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2032 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-119 | + | Lemoyne 345 kV | OH | Wood | Withdrawn | ATSI | 1260 | 550 | 550 | Capacity | Generation Interconnection | Natural Gas; Other | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1119_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1119_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 9/17/2018 | N/A | N/A | 10/27/2021 | 6/1/2022 | N/A | N | No | |||||||||||||||||
| AE1-119 | - | Lemoyne 345 kV | OH | Wood | Active | ATSI | 1260 | 550 | 550 | Capacity | Generation Interconnection | Natural Gas; Other | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1119_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1119_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2018 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AE1-129 | + | Zion View - Middletown 115 kV | Strinestown Solar Project | PA | York | Engineering and Procurement | ME | 79.6 | 79.6 | 47 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1129_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1129_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1129_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_129_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_129_csa.pdf | Document Posted | N/A | N/A | 9/7/2018 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||
| AE1-129 | - | Zion View - Middletown 115 kV | Strinestown Solar Project | PA | York | Engineering and Procurement | ME | 79.6 | 79.6 | 47 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1129_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1129_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1129_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_129_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_129_csa | Document Posted | N/A | N/A | 9/7/2018 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||
| AE1-154 | + | Louisa-South Anna 230 kV | Belcher Solar | VA | Louisa | Engineering and Procurement | Dominion | 105.2 | 17 | 10 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1154_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1154_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ae1_154_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_154_csa.pdf | Document Posted | N/A | N/A | 9/24/2018 | N/A | N/A | 12/1/2022 | 12/1/2021 | 12/1/2021 | N/A | N | No | ||||||||||
| AE1-154 | - | Louisa-South Anna 230 kV | Belcher Solar | VA | Louisa | Engineering and Procurement | Dominion | 105.2 | 17 | 10 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1154_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1154_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ae1_154_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_154_csa.pdf | Document Posted | N/A | N/A | 9/24/2018 | N/A | N/A | 12/1/2021 | 12/1/2021 | 12/1/2021 | N/A | N | No | ||||||||||
| AE1-155 | + | Garner-Northern Neck 115 kV | VA | City of Richmond | Active | Dominion | 127 | 127 | 76.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1155_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1155_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/ae1_155_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/24/2018 | N/A | N/A | 10/23/2020 | N/A | N | No | |||||||||||||||
| AE1-155 | - | Garner-Northern Neck 115 kV | VA | City of Richmond | Active | Dominion | 127 | 127 | 76.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1155_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1155_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/24/2018 | N/A | N/A | 10/23/2020 | N/A | N | No | ||||||||||||||||||
| AE1-183 | + | Maysville-McDowell 69 kV | Jackson Center Solar Facility | PA | Mercer | Suspended | ATSI | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1183_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1183_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1183_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_183_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_183_csa.pdf | Document Posted | N/A | N/A | 9/25/2018 | N/A | N/A | 5/15/2023 | 5/15/2023 | N/A | N | No | ||||||||||
| AE1-183 | - | Maysville-McDowell 69 kV | Jackson Center Solar Facility | PA | Mercer | Engineering and Procurement | ATSI | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1183_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1183_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1183_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_183_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_183_csa.pdf | Document Posted | N/A | N/A | 9/25/2018 | N/A | N/A | 5/15/2023 | 5/15/2023 | N/A | N | No | ||||||||||
| AE1-196 | + | Hokes-Jackson 69 kV II | Cottontail Solar 8 | PA | York | Engineering and Procurement | ME | 20 | 20 | 12.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1196_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1196_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1196_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae1_196_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae1_196_csa.pdf | Document Posted | N/A | N/A | 9/26/2018 | N/A | N/A | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||||
| AE1-196 | - | Hokes-Jackson 69 kV II | PA | York | Active | ME | 20 | 20 | 12.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1196_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1196_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae1196_fac.pdf | Document Posted | N/A | N/A | 9/26/2018 | N/A | N/A | 4/1/2021 | N/A | N | No | |||||||||||||||||
| AE1-230 | + | Shockoe 69 kV | VA | Pittsylvania | Withdrawn | Dominion | 20 | 20 | 7.2 | Capacity | Generation Interconnection | Storage; Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1230_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1230_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2018 | N/A | N/A | 9/1/2021 | 7/31/2020 | N/A | N | No | |||||||||||||||||
| AE1-230 | - | Shockoe 69 kV | VA | Pittsylvania | Active | Dominion | 20 | 20 | 7.2 | Capacity | Generation Interconnection | Storage; Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1230_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1230_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2018 | N/A | N/A | 7/31/2020 | N/A | N | No | ||||||||||||||||||
| AE1-231 | + | Hughesville 69 kV | MD | Charles | Withdrawn | SMECO | 20 | 20 | 9.4 | Capacity | Generation Interconnection | Storage; Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1231_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1231_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 9/28/2018 | N/A | N/A | 9/3/2021 | 7/31/2020 | N/A | N | No | |||||||||||||||||
| AE1-231 | - | Hughesville 69 kV | MD | Charles | Active | SMECO | 20 | 20 | 9.4 | Capacity | Generation Interconnection | Storage; Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1231_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1231_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2018 | N/A | N/A | 7/31/2020 | N/A | N | No | ||||||||||||||||||
| AE2-005 | + | Harmony Village-Shackleford 115 kV | Walnut Solar I | VA | King and Queen | Engineering and Procurement | Dominion | 130 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2005_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2005_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ae2_005_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2_005_csa.pdf | Document Posted | N/A | N/A | 10/4/2018 | N/A | N/A | 12/31/2022 | 12/31/2022 | N/A | N | No | |||||||||||
| AE2-005 | - | Harmony Village-Shackleford 115 kV | Walnut Solar I | VA | King and Queen | Engineering and Procurement | Dominion | 130 | 20 | 7.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2005_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2005_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ae2_005_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 10/4/2018 | N/A | N/A | 12/31/2022 | 12/31/2022 | N/A | N | No | ||||||||||||
| AE2-022 | + | Cardiff 230 kV III | NJ | Atlantic | Active | AEC | 300 | 300 | 52.8 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2022_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2022_imp.pdf | Document Posted | In Progress | N/A | N/A | 12/14/2018 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AE2-022 | - | Cardiff 230 kV III | NJ | Atlantic | Active | AEC | 300 | 300 | 62.09 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2022_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2022_imp.pdf | Document Posted | In Progress | N/A | N/A | 12/14/2018 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AE2-035 | + | Lena 138 kV | High Point II Solar | IL | Stephenson | Engineering and Procurement | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2035_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2035_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2035_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae2_035_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2_035_csa.pdf | Document Posted | N/A | N/A | 1/15/2019 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | ||||||||||
| AE2-035 | - | Lena 138 kV | IL | Stephenson | Active | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2035_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2035_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2035_fac.pdf | Document Posted | N/A | N/A | 1/15/2019 | N/A | N/A | 5/21/2021 | N/A | N | No | |||||||||||||||||
| AE2-042 | + | Milton 69 kV | Northumberland Solar | PA | Northumberland | Engineering and Procurement | PPL | 70 | 70 | 46.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2042_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2042_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2042_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae2_042_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2_042_csa.pdf | Document Posted | N/A | N/A | 1/23/2019 | N/A | N/A | 3/24/2023 | 3/24/2023 | N/A | N | No | ||||||||||
| AE2-042 | - | Milton 69 kV | Northumberland Solar | PA | Northumberland | Engineering and Procurement | PPL | 70 | 70 | 46.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2042_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2042_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2042_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae2042_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2042_csa.pdf | Document Posted | N/A | N/A | 1/23/2019 | N/A | N/A | 3/24/2023 | 3/24/2023 | N/A | N | No | ||||||||||
| AE2-059 | + | Derry Tap-Derry Bus 69 kV | PA | Northumberland | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2059_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2059_fac.pdf | Document Posted | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | |||||||||||||||||
| AE2-059 | - | Derry Tap-Derry Bus 69 kV | PA | Northumberland | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2059_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | ||||||||||||||||||
| AE2-060 | + | Mifflintown Bus-Mifflintown Tap 69 kV | PA | Juniata | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2060_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2060_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2060_fac.pdf | Document Posted | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | |||||||||||||||||
| AE2-060 | - | Mifflintown Bus-Mifflintown Tap 69 kV | PA | Juniata | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2060_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2060_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | ||||||||||||||||||
| AE2-084 | + | Derry Tap-Derry Bus 69 kV | PA | Montour | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2084_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2084_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2084_fac.pdf | Document Posted | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | |||||||||||||||||
| AE2-084 | - | Derry Tap-Derry Bus 69 kV | PA | Montour | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2084_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2084_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/1/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | ||||||||||||||||||
| AE2-091 | + | Newport 69 kV | NJ | Cumberland | Withdrawn | Unknown | 35 | 35 | 23 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2091_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2091_imp.pdf | Document Posted | N/A | N/A | 1/24/2019 | N/A | N/A | 3/31/2020 | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AE2-091 | - | Newport 69 kV | NJ | Cumberland | Withdrawn | AEC | 35 | 35 | 23 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2091_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2091_imp.pdf | Document Posted | N/A | N/A | 1/24/2019 | N/A | N/A | 3/31/2020 | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AE2-104 | + | Suffolk 115 kV | VA | Accomack | Active | Dominion | 49 | 49 | 18.92 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2104_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2019 | N/A | N/A | 11/30/2021 | N/A | N | No | ||||||||||||||||||
| AE2-104 | - | Suffolk 115 kV | VA | City of Suffolk | Active | Dominion | 49 | 49 | 18.92 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2104_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2019 | N/A | N/A | 11/30/2021 | N/A | N | No | ||||||||||||||||||
| AE2-113 | + | Farmers Valley-Ridgeway 115 kV | PA | McKean | Active | PENELEC | 120 | 120 | 61.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2113_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2113_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2019 | N/A | N/A | 12/31/2020 | N/A | N | No | ||||||||||||||||||
| AE2-113 | - | Farmers Valley-Ridgeway 115 kV | PA | McKean | Active | APS | 120 | 120 | 61.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2113_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2113_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2019 | N/A | N/A | 12/31/2020 | N/A | N | No | ||||||||||||||||||
| AE2-133 | + | Penns Tap-Richfield Tie 69 kV | PA | Snyder | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2133_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2133_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2133_fac.pdf | Document Posted | N/A | N/A | 2/28/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | |||||||||||||||||
| AE2-133 | - | Penns Tap-Richfield Tie 69 kV | PA | Snyder | Active | PPL | 20 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2133_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2133_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2019 | N/A | N/A | 3/5/2021 | N/A | N | No | ||||||||||||||||||
| AE2-148 | + | Beatty-Greene 345 kV | OH | Madison | Active | AEP | 577 | 577 | 397.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2148_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2148_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/ae2_148_isa2.pdf | Interim Study | N/A | Not Required | N/A | N/A | 2/20/2019 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||
| AE2-148 | - | Beatty-Greene 345 kV | OH | Madison | Active | AEP | 577 | 577 | 397.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2148_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2148_imp.pdf | Document Posted | In Progress | Not Required | N/A | N/A | 2/20/2019 | N/A | N/A | 6/1/2022 | N/A | N | No | |||||||||||||||||
| AE2-169 | + | Delaware-Van Buren 138 kV | IN | Delaware | Active | AEP | 163 | 33 | 33 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2169_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2169_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/15/2019 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AE2-169 | - | Delaware-Van Buren 138 kV | IN | Delaware | Active | AEP | 163 | 33 | 33 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2169_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2169_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/15/2019 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AE2-218 | + | Eldean 138 kV | OH | Miami | Active | Dayton | 178 | 178 | 106 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2218_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2218_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2218_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/csa/ae2_218_csa.pdf | Document Posted | N/A | N/A | 3/21/2019 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||
| AE2-218 | - | Eldean 138 kV | OH | Miami | Active | Dayton | 178 | 178 | 106 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2218_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2218_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2218_fac.pdf | Document Posted | N/A | N/A | 3/21/2019 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||||
| AE2-282 | + | East Fayette 138 kV | OH | Fulton | Engineering and Procurement | ATSI | 67 | 67 | 43.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2282_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2282_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/ae2_282_isa2.pdf | Interim Study | N/A | N/A | N/A | 3/29/2019 | N/A | N/A | 9/15/2021 | N/A | N | No | |||||||||||||||
| AE2-282 | - | East Fayette 138 kV | OH | Fulton | Active | ATSI | 67 | 67 | 43.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2282_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2282_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/ae2_282_isa2.pdf | Interim Study | N/A | N/A | N/A | 3/29/2019 | N/A | N/A | 9/15/2021 | N/A | N | No | |||||||||||||||
| AE2-285 | + | Maysville 69 kV | MC Solar I | PA | Mercer | Suspended | ATSI | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2285_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2285_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2285_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae2_285_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2_285_csa.pdf | Document Posted | N/A | N/A | 3/29/2019 | N/A | N/A | 1/2/2023 | 1/2/2023 | N/A | N | No | ||||||||||
| AE2-285 | - | Maysville 69 kV | MC Solar I | PA | Mercer | Engineering and Procurement | ATSI | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2285_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2285_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2285_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ae2_285_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ae2_285_csa.pdf | Document Posted | N/A | N/A | 3/29/2019 | N/A | N/A | 1/2/2023 | 1/2/2023 | N/A | N | No | ||||||||||
| AE2-319 | + | Atlanta 69kV I | OH | Pickaway | Active | Dayton | 100 | 100 | 66.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2319_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2319_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2019 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||
| AE2-319 | - | Atlanta 69kV I | OH | Pickaway | Active | Dayton | 100 | 100 | 66.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2319_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2319_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2019 | N/A | N/A | 4/1/2019 | 12/1/2022 | N/A | N | No | |||||||||||||||||
| AE2-343 | + | Andover (Maysville) 69 kV II | PA | Crawford | Active | ATSI | 17.9 | 17.9 | 12.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2343_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2343_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2343_fac.pdf | Document Posted | N/A | N/A | 3/31/2019 | N/A | N/A | 9/30/2020 | N/A | N | No | |||||||||||||||||
| AE2-343 | - | Andover (Maysville) 69 kV II | PA | Crawford | Active | ATSI | 17.9 | 17.9 | 12.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2343_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2343_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2019 | N/A | N/A | 9/30/2020 | N/A | N | No | ||||||||||||||||||
| AF1-001 | + | Thayerville 34.5 kV | Sand Flat Road Solar Project | MD | Garrett | Suspended | APS | 13.8 | 13.75 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1001_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1001_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1001_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1001_wmpa.pdf | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||||
| AF1-001 | - | Thayerville 34.5 kV | Sand Flat Road Solar Project | MD | Garrett | Engineering and Procurement | APS | 13.8 | 13.75 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1001_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1001_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1001_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1001_wmpa.pdf | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||||
| AF1-003 | + | Hawkins Gate-Billingsley Rd 69 kV | Charles County Solar II | MD | Charles | Engineering and Procurement | SMECO | 20 | 20 | 9.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1003_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1003_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/af1003_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1003_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1003_wmpa.pdf | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 9/30/2024 | 9/30/2024 | N/A | N | No | ||||||||||
| AF1-003 | - | Hawkins Gate-Billingsley Rd 69 kV | MD | Charles | Active | SMECO | 20 | 20 | 9.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1003_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1003_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/af1003_fac.pdf | Document Posted | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 7/30/2021 | N/A | N | No | ||||||||||||||||
| AF1-005 | + | Grayton-Ripley 69 kV | Charles County Solar I | MD | Charles | Engineering and Procurement | SMECO | 20 | 20 | 9.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1005_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1005_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/af1005_fac.pdf | Document Posted | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1005_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1005_wmpa.pdf | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 9/30/2024 | 9/30/2024 | N/A | N | No | ||||||||||
| AF1-005 | - | Charles County Solar I | MD | Charles | Active | SMECO | 20 | 20 | 9.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1005_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1005_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/af1005_fac.pdf | Document Posted | Not Required | N/A | N/A | 4/1/2019 | N/A | N/A | 7/30/2021 | N/A | N | No | ||||||||||||||||
| AF1-014 | + | Harmony Village-Shackleford 115 kV | Walnut Solar I | VA | King and Queen | Engineering and Procurement | Dominion | 149.9 | 19.9 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1014_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1014_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af1_014_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/af1_014_csa.pdf | Document Posted | N/A | N/A | 4/3/2019 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | |||||||||||
| AF1-014 | - | Harmony Village-Shackleford 115 kV | Walnut Solar I | VA | King and Queen | Engineering and Procurement | Dominion | 149.9 | 19.9 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1014_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1014_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af1_014_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 4/3/2019 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||||
| AF1-028 | + | Endless Caverns 115 kV | VA | Rockingham | Active | Dominion | 200 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1028_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1028_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/13/2019 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AF1-028 | - | Endless Caverns 115 kV | VA | Rockingham | Active | Dominion | 200 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1028_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1028_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/13/2019 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AF1-099 | + | Moshannon-Milesburg 230 kV | PA | Huntingdon | Active | APS | 126.5 | 126.5 | 75.9 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1099_fea.pdf | Document Posted | N/A | N/A | 9/4/2019 | N/A | N/A | 4/1/2022 | N/A | N | No | |||||||||||||||||||||
| AF1-099 | - | Moshannon-Milesburg 230 kV | PA | Huntingdon | Active | APS | 126.5 | 126.5 | 75.9 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1099_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/4/2019 | N/A | N/A | 4/1/2022 | N/A | N | No | ||||||||||||||||||||
| AF1-123 | + | Oceana 230 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1123_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1123_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_123_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2025 | N/A | N | No | |||||||||||||||
| AF1-123 | - | Fentress 500 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1123_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1123_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_123_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2025 | N/A | N | No | |||||||||||||||
| AF1-124 | + | Oceana 230 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1124_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1124_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_124_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2026 | N/A | N | No | |||||||||||||||
| AF1-124 | - | Fentress 500 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1124_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1124_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_124_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2026 | N/A | N | No | |||||||||||||||
| AF1-125 | + | Oceana 230 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1125_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1125_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_125_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2024 | N/A | N | No | |||||||||||||||
| AF1-125 | - | Fentress 500 kV | VA | City of Chesapeake | Active | Dominion | 880 | 880 | 267.5 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1125_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1125_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_125_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/17/2019 | N/A | N/A | 12/31/2024 | N/A | N | No | |||||||||||||||
| AF1-140 | + | Claysburg 23 kV | BL-Diamond Bear Rocks | PA | Adams | Suspended | PENELEC | 16.3 | 16.3 | 9.78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1140_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1140_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1140_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1140_wmpa.pdf | Not Required | N/A | N/A | 9/18/2019 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||||
| AF1-140 | - | Claysburg 23 kV | BL-Diamond Bear Rocks | PA | Blair | Suspended | PENELEC | 16.3 | 16.3 | 9.78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1140_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1140_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1140_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1140_wmpa.pdf | Not Required | N/A | N/A | 9/18/2019 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||||
| AF1-147 | + | Poland Rd-Runway DP 230kV | Dulles Solar | VA | Loudoun | Engineering and Procurement | Dominion | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1147_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1147_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/af1147_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/af1_147_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/af1_147_csa.pdf | Document Posted | N/A | N/A | 9/19/2019 | N/A | N/A | 12/31/2023 | 12/31/2023 | N/A | N | No | ||||||||||
| AF1-147 | - | Poland Rd-Runway DP 230kV | VA | Loudoun | Active | Dominion | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1147_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1147_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/19/2019 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AF1-150 | + | Midfield 22.9 kV | Pittsburgh International Airport | PA | Allegheny | In Service | DL | 14.4 | 14.4 | 4.28 | 14.4 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1150_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1150_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1150_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1150_wmpa.pdf | Not Required | N/A | N/A | 4/1/2021 | 9/19/2019 | N/A | N/A | 4/1/2021 | 9/1/2021 | 9/1/2021 | 10/28/2021 | N/A | N | No | |||||||
| AF1-150 | - | Midfield 22.9 kV | Pittsburgh International Airport | PA | Allegheny | Under Construction | DL | 14.4 | 14.4 | 4.28 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1150_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1150_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af1150_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af1150_wmpa.pdf | Not Required | N/A | N/A | 4/1/2021 | 9/19/2019 | N/A | N/A | 4/1/2021 | 9/1/2021 | 9/1/2021 | N/A | N | No | |||||||||
| AF1-215 | + | Reynolds-Olive 345 kV | IN | Starke | Active | AEP | 300 | 300 | 180 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1215_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1215_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_215_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/26/2019 | N/A | N/A | 5/31/2021 | N/A | N | No | |||||||||||||||
| AF1-215 | - | Reynolds-Olive 345 kV | IN | Starke | Active | AEP | 300 | 300 | 180 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1215_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1215_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/26/2019 | N/A | N/A | 5/31/2021 | N/A | N | No | ||||||||||||||||||
| AF1-227 | + | Marysville – Gunn Road 345 kV | OH | Union | Active | AEP | 325 | 325 | 195 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1227_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1227_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_227_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/27/2019 | N/A | N/A | 5/31/2022 | N/A | N | No | |||||||||||||||
| AF1-227 | - | Marysville-East Lima 345 kV | OH | Union | Active | AEP | 325 | 325 | 195 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1227_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1227_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_227_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/27/2019 | N/A | N/A | 5/31/2022 | N/A | N | No | |||||||||||||||
| AF1-230 | + | Chatfield 138 kV | OH | Crawford | Withdrawn | Unknown | 49 | 49 | 29.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1230_fea.pdf | Document Posted | N/A | N/A | 9/27/2019 | N/A | N/A | 2/5/2020 | 10/31/2022 | N/A | N | No | ||||||||||||||||||||
| AF1-230 | - | Chatfield 138 kV | OH | Crawford | Withdrawn | AEP | 49 | 49 | 29.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1230_fea.pdf | Document Posted | N/A | N/A | 9/27/2019 | N/A | N/A | 2/5/2020 | 10/31/2022 | N/A | N | No | ||||||||||||||||||||
| AF1-250 | + | Maysville 69 kV II | PA | Mercer | Withdrawn | ATSI | 68 | 18 | 10.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1250_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1250_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 9/30/2019 | N/A | N/A | 9/24/2021 | 6/30/2022 | N/A | N | No | |||||||||||||||||
| AF1-250 | - | Maysville 69 kV II | PA | Mercer | Active | ATSI | 68 | 18 | 10.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1250_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1250_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2019 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AF1-265 | + | Four Rivers-Hanover 230 kV | VA | Hanover | Active | Dominion | 435 | 150 | 150 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1265_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1265_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2019 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AF1-265 | - | Four Rivers-Hanover 230 kV | VA | Hanover | Active | Dominion | 450 | 150 | 150 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1265_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1265_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2019 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AF1-271 | + | Keisters-Krendale 138 kV | PA | Butler | Withdrawn | APS | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1271_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1271_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 9/30/2019 | N/A | N/A | 10/11/2021 | 12/31/2023 | N/A | N | No | |||||||||||||||||
| AF1-271 | - | Keisters-Krendale 138 kV | PA | Butler | Active | APS | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1271_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1271_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2019 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AF1-290 | + | Feagans Mill-Millville 138 kV | WV | Jefferson | Active | APS | 80 | 80 | 40.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1290_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1290_imp.pdf | Document Posted | In Progress | https://www.pjm.com/pub/planning/project-queues/isa/af1_290_isa2.pdf | Interim Study | N/A | N/A | N/A | 9/30/2019 | N/A | N/A | 6/14/2021 | N/A | N | No | |||||||||||||||
| AF1-290 | - | Feagans Mill-Millville 138 kV | WV | Jefferson | Active | APS | 80 | 80 | 40.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af1290_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af1290_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2019 | N/A | N/A | 6/14/2021 | N/A | N | No | ||||||||||||||||||
| AF2-018 | + | Inez 138 kV | KY | Martin | Active | AEP | 200 | 200 | 133.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2018_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2018_imp.pdf | Document Posted | In Progress | N/A | N/A | 11/1/2019 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AF2-018 | - | Inez 138 kV | KY | Martin | Active | AEP | 200 | 200 | 133.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2018_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2018_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 11/1/2019 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AF2-019 | + | Middle 69 kV | NJ | Cape May | Active | AEC | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2019_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2019_imp.pdf | Document Posted | In Progress | N/A | N/A | 11/15/2019 | N/A | N/A | 6/1/2021 | N/A | N | No | ||||||||||||||||||
| AF2-019 | - | Middle 69 kV | NJ | Cape May | Active | AEC | 20 | 40 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2019_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2019_imp.pdf | Document Posted | In Progress | N/A | N/A | 11/15/2019 | N/A | N/A | 6/1/2021 | N/A | N | No | ||||||||||||||||||
| AF2-045 | + | Cambria Nug 115 kV | Cambria Energy | PA | Cambria | Withdrawn | PENELEC | 20 | 20 | 2 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2045_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2045_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af2_045_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 12/13/2019 | N/A | N/A | 10/8/2021 | 9/30/2022 | 9/30/2022 | N/A | N | No | |||||||||||
| AF2-045 | - | Cambria Nug 115 kV | Cambria Energy | PA | Cambria | Engineering and Procurement | PENELEC | 20 | 20 | 2 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2045_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2045_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af2_045_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 12/13/2019 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | N | No | ||||||||||||
| AF2-057 | + | Grassfield 34.5 kV | Cedar Energy Center | VA | City of Chesapeake | Engineering and Procurement | Dominion | 20 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2057_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2057_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2057_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2057_wmpa.pdf | Not Required | N/A | N/A | 1/22/2020 | N/A | N/A | 12/1/2024 | 12/1/2024 | N/A | N | No | |||||||||||
| AF2-057 | - | Grassfield 34.5 kV | VA | City of Chesapeake | Active | Dominion | 20 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2057_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2057_imp.pdf | Document Posted | In Progress | N/A | N/A | 1/22/2020 | N/A | N/A | 4/1/2022 | N/A | N | No | ||||||||||||||||||
| AF2-110 | + | Suffolk 115 kV | VA | Accomack | Active | Dominion | 69 | 20 | 7.72 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2110_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2110_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/26/2020 | N/A | N/A | 11/30/2021 | N/A | N | No | ||||||||||||||||||
| AF2-110 | - | Suffolk 115 kV | VA | City of Suffolk | Active | Dominion | 69 | 20 | 7.72 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2110_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2110_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/26/2020 | N/A | N/A | 11/30/2021 | N/A | N | No | ||||||||||||||||||
| AF2-112 | + | Oakland-Gorman 69 kV | Webb Solar | MD | Garrett | Active | APS | 10 | 10 | 6.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2112_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2112_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | |||||||||||||||||
| AF2-112 | - | Oakland-Gorman 69 kV | MD | Garrett | Active | APS | 17 | 17 | 11.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2112_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2112_imp.pdf | Document Posted | In Progress | N/A | N/A | 2/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AF2-144 | + | Powhatan 34.5 kV | Scott 1 BESS | VA | Powhatan | Engineering and Procurement | Dominion | 17 | 17 | 10.2 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2144_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2144_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2144_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2144_wmpa.pdf | Not Required | N/A | N/A | 3/12/2020 | N/A | N/A | 6/1/2023 | 6/1/2023 | N/A | N | No | |||||||||||
| AF2-144 | - | Powhatan 34.5 kV | VA | Powhatan | Active | Dominion | 17 | 17 | 10.2 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2144_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2144_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/12/2020 | N/A | N/A | 6/1/2021 | N/A | N | No | ||||||||||||||||||
| AF2-151 | + | Dillsburg 13.2 kV | PA York Hess | PA | York | Suspended | ME | 3 | 3 | 1.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2151_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2151_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2151_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2151_wmpa.pdf | Not Required | N/A | N/A | 3/16/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | N | No | |||||||||||
| AF2-151 | - | Dillsburg 13.2 kV | PA York Hess | PA | York | Engineering and Procurement | ME | 3 | 3 | 1.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2151_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2151_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2151_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2151_wmpa.pdf | Not Required | N/A | N/A | 3/16/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | N | No | |||||||||||
| AF2-185 | + | Mercersburg-Milnor 34.5 kV II | Elk Hill Solar 2 | PA | Franklin | In Service | APS | 15 | 0 | 4.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2185_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2185_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af2_185_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 3/20/2020 | N/A | N/A | 9/1/2022 | 9/1/2022 | 1/4/2021 | N/A | N | No | |||||||||||
| AF2-185 | - | Mercersburg-Minor 34 kV II | Elk Hill Solar 2 | PA | Franklin | In Service | APS | 15 | 0 | 4.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2185_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2185_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/af2_185_isa.pdf | Document Posted | N/A | Not Required | N/A | N/A | 3/20/2020 | N/A | N/A | 9/1/2022 | 9/1/2022 | 1/4/2021 | N/A | N | No | |||||||||||
| AF2-186 | + | South Cecil 69 kV | OH | Paulding | Active | AEP | 45 | 45 | 18.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2186_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2186_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AF2-186 | - | South Cecil 69 kV | OH | Paulding | Active | AEP | 45 | 45 | 18.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2186_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AF2-187 | + | Brookside-Cloverdale 138 kV | OH | Wayne | Active | ATSI | 130 | 130 | 78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2187_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2187_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/22/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AF2-187 | - | Brookside-Cloverdale 138 kV | OH | Wayne | Active | ATSI | 130 | 130 | 78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2187_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2187_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/22/2020 | N/A | N/A | 9/21/2020 | 6/30/2023 | N/A | N | No | |||||||||||||||||
| AF2-189 | + | Greentown 138 kV | IN | Howard | Withdrawn | AEP | 150 | 150 | 90 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2189_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2189_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 3/22/2020 | N/A | N/A | 9/17/2021 | 6/30/2023 | N/A | N | No | |||||||||||||||||
| AF2-189 | - | Greentown 138 kV | IN | Howard | Active | AEP | 150 | 150 | 90 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2189_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2189_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/22/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AF2-221 | + | Scalp Level 22.9 kV | PA | Somerset | Active | PENELEC | 15 | 15 | 6.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2221_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/25/2020 | N/A | N/A | 3/15/2023 | N/A | N | No | ||||||||||||||||||||
| AF2-221 | - | Scalp Level 22.9 kV | PA | Somerset | Active | PENELEC | 15 | 15 | 6.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2221_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/25/2020 | N/A | N/A | 10/28/2020 | 3/15/2023 | N/A | N | No | |||||||||||||||||||
| AF2-268 | + | Orrtanna 13.2 kV | AD-Chambersburg | PA | Adams | Suspended | ME | 2 | 2 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2268_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2268_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2268_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2268_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-268 | - | Orrtanna 13.2 kV | AD-Chambersburg | PA | Adams | Engineering and Procurement | ME | 2 | 2 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2268_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2268_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2268_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2268_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-271 | + | Pemberton-Sinking Valley 12.47 kV | BL-Kettle | PA | Blair | Suspended | PENELEC | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2271_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2271_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2271_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2271_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-271 | - | Pemberton-Sinking Valley 12.47 kV | BL-Kettle | PA | Blair | Engineering and Procurement | PENELEC | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2271_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2271_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2271_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2271_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-272 | + | Bernville 13.2 kV | BR-Swissdale | PA | Blair | Suspended | ME | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2272_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2272_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2272_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2272_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-272 | - | Bernville 13.2 kV | BR-Swissdale | PA | Blair | Engineering and Procurement | ME | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2272_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2272_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2272_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2272_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | Y | No | |||||||||||
| AF2-276 | + | Guilford 12.47 kV | FR-Statler | PA | Franklin | Engineering and Procurement | APS | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2276_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2276_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2276_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2276_wmpa.pdf | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 3/31/2023 | 3/31/2023 | N/A | Y | No | |||||||||||
| AF2-276 | - | Guilford 12.47 kV | PA | Franklin | Active | APS | 3 | 3 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2276_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2276_imp.pdf | Document Posted | Not Required | Not Required | N/A | N/A | 3/27/2020 | N/A | N/A | 7/1/2021 | N/A | Y | No | |||||||||||||||||
| AF2-303 | + | Edgecombe 230 kV | NC | Edgecombe | Active | Dominion | 100 | 100 | 100 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2303_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2303_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2020 | N/A | N/A | 8/3/2023 | N/A | N | No | This project slid to the next queue | |||||||||||||||||
| AF2-303 | - | Edgecombe 230 kV | NC | Edgecombe | Active | Dominion | 100 | 100 | 100 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2303_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2020 | N/A | N/A | 8/3/2023 | N/A | N | No | This project slid to the next queue | |||||||||||||||||||
| AF2-304 | + | Surry-Hopewell 230 kV | VA | Surry | Active | Dominion | 89 | 89 | 89 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2304_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2304_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2020 | N/A | N/A | 8/3/2023 | N/A | N | No | This project slid to the next queue | |||||||||||||||||
| AF2-304 | - | Surry-Hopewell 230 kV | VA | Surry | Active | Dominion | 89 | 89 | 89 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2304_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2020 | N/A | N/A | 8/3/2023 | N/A | N | No | This project slid to the next queue | |||||||||||||||||||
| AF2-314 | + | Vandergrift-Guffy Junction 25 kV | Ponytail Solar | PA | Armstrong | Suspended | APS | 10 | 10 | 6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2314_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2314_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2314_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2314_wmpa.pdf | Not Required | N/A | N/A | 3/30/2020 | N/A | N/A | 9/30/2023 | 9/30/2023 | N/A | N | No | |||||||||||
| AF2-314 | - | Vandergrift-Guffy Junction 25 kV | PA | Armstrong | Active | APS | 10 | 10 | 6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2314_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2314_imp.pdf | Document Posted | Not Required | Not Required | N/A | N/A | 3/30/2020 | N/A | N/A | 9/1/2022 | N/A | N | No | |||||||||||||||||
| AF2-324 | + | Edgecombe 230 kV | NC | Edgecombe | Active | Dominion | 75 | 75 | 48.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2324_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/30/2020 | N/A | N/A | 11/30/2022 | N/A | N | No | ||||||||||||||||||||
| AF2-324 | - | Edgecombe 230 kV | NC | Edgecombe | Active | Dominion | 75 | 75 | 48.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2324_fea.pdf | Document Posted | N/A | N/A | 3/30/2020 | N/A | N/A | 11/30/2022 | N/A | N | No | |||||||||||||||||||||
| AF2-343 | + | Maysville 138 kV III | PA | Mercer | Withdrawn | ATSI | 60 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2343_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2343_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 3/31/2020 | N/A | N/A | 7/23/2021 | 12/31/2023 | N/A | N | No | |||||||||||||||||
| AF2-343 | - | Maysville 138 kV III | PA | Mercer | Active | ATSI | 60 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2343_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2343_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 3/31/2020 | N/A | N/A | 7/23/2021 | 12/31/2023 | N/A | N | No | |||||||||||||||||
| AF2-385 | + | Nelson 69 kV | DE | Sussex | Withdrawn | DPL | 75 | 75 | 47.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2385_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2385_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 3/31/2020 | N/A | N/A | 10/14/2021 | 10/31/2022 | N/A | N | No | |||||||||||||||||
| AF2-385 | - | Nelson 69 kV | DE | Sussex | Active | DPL | 75 | 75 | 47.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2385_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2385_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||
| AF2-395 | + | Flatlick 765 kV | OH | Vinton | Active | AEP | 1045 | 51.1 | 89.6 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2395_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2395_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2020 | N/A | N/A | 5/1/2022 | N/A | N | No | ||||||||||||||||||
| AF2-395 | - | Flatlick 765 kV | OH | Vinton | Active | AEP | 1045 | 51.1 | 89.6 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2395_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2395_imp.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2020 | N/A | N/A | 3/31/2021 | 5/1/2022 | N/A | N | No | |||||||||||||||||
| AF2-398 | + | Necessity-Dinnerbell 12.47 kV | Fike Solar | PA | Fayette | Engineering and Procurement | APS | 3 | 3 | 1.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2398_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2398_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/af2398_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/af2398_wmpa.pdf | Not Required | N/A | N/A | 3/31/2020 | N/A | N/A | 9/30/2023 | 9/30/2023 | N/A | N | No | |||||||||||
| AF2-398 | - | Necessity-Dinnerbell 12.47 kV | PA | Fayette | Active | APS | 3 | 3 | 1.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2398_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/af2398_imp.pdf | Document Posted | Not Required | Not Required | N/A | N/A | 3/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||||
| AF2-412 | + | Mainesburg 115 kV | PA | Tioga | Active | PENELEC | 130 | 130 | 130 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2412_fea.pdf | Document Posted | Withdrawn | N/A | N/A | 3/31/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AF2-412 | - | Mainesburg 115 kV | PA | Tioga | Active | PENELEC | 130 | 130 | 130 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2412_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AF2-419 | + | Hunt Farm-Ballard 69 kV | KY | Boyle | Withdrawn | EKPC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2419_fea.pdf | Document Posted | Withdrawn | N/A | N/A | 3/31/2020 | N/A | N/A | 9/14/2020 | 11/1/2021 | N/A | N | No | |||||||||||||||||||
| AF2-419 | - | Hunt Farm-Ballard 69 kV | KY | Boyle | Withdrawn | EKPC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/af2419_fea.pdf | Document Posted | In Progress | N/A | N/A | 3/31/2020 | N/A | N/A | 9/14/2020 | 11/1/2021 | N/A | N | No | |||||||||||||||||||
| AG1-001 | + | US Silica-Unimin 69 kV | NJ | Cumberland | Active | AEC | 31 | 31 | 11.78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1001_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1001_imp.pdf | Document Posted | In Progress | N/A | N/A | 4/3/2020 | N/A | N/A | 3/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-001 | - | US Silica-Unimin 69 kV | NJ | Cumberland | Active | AEC | 31 | 31 | 11.78 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1001_fea.pdf | Document Posted | In Progress | N/A | N/A | 4/3/2020 | N/A | N/A | 3/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-003 | + | Marysville-Sorenson 765 kV | OH | Logan | Active | AEP | 900 | 400 | 226 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1003_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1003_imp.pdf | Document Posted | In Progress | N/A | N/A | 4/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-003 | - | Marysville-Sorenson 765 kV | OH | Logan | Active | AEP | 900 | 400 | 226 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1003_fea.pdf | Document Posted | In Progress | N/A | N/A | 4/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-004 | + | Marysville-Sorenson 765 kV | OH | Logan | Active | AEP | 1100 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1004_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1004_imp.pdf | Document Posted | In Progress | N/A | N/A | 4/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-004 | - | Marysville-Sorenson 765 kV | OH | Logan | Active | AEP | 1100 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1004_fea.pdf | Document Posted | In Progress | N/A | N/A | 4/20/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-007 | + | Tar River 12.5 kV | NC | Edgecombe | Active | Dominion | 9.4 | 9.4 | 6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1007_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1007_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/1/2020 | N/A | N/A | 12/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-007 | - | Tar River 12.5 kV | NC | Edgecombe | Active | Dominion | 9.4 | 9.4 | 6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1007_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/1/2020 | N/A | N/A | 12/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-009 | + | Hopewell-Surry 230kV | VA | Surry | Active | Dominion | 150 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1009_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1009_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/4/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-009 | - | Hopewell-Surry 230kV | VA | Surry | Active | Dominion | 150 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1009_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/4/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-010 | + | Ladysmith-CT-St. Johns 230 kV | VA | Caroline | Active | Dominion | 180 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1010_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1010_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/5/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-010 | - | Ladysmith-CT-St. Johns 230 kV | VA | Caroline | Active | Dominion | 180 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1010_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/5/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-012 | + | Mewdow Brook-Strasburg 138 kV II | VA | Frederick | Active | APS | 75 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1012_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1012_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-012 | - | Mewdow Brook-Strasburg 138 kV II | VA | Frederick | Active | APS | 75 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1012_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-013 | + | Ladysmith CT-St. Johns 230 kV | VA | Caroline | Active | Dominion | 120 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1013_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1013_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-013 | - | Ladysmith CT-St. Johns 230 kV | VA | Caroline | Active | Dominion | 120 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1013_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-014 | + | Carson-Rogers Rd 500 kV | VA | Greensville | Active | Dominion | 500 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1014_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1014_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||
| AG1-014 | - | Carson-Rogers Rd 500 kV | VA | Greensville | Active | Dominion | 500 | 0 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1014_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-015 | + | Carson-Rogers Rd 500 kV | VA | Greensville | Active | Dominion | 400 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1015_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1015_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||
| AG1-015 | - | Carson-Rogers Rd 500 kV | VA | Greensville | Active | Dominion | 400 | 0 | 0 | Energy | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1015_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/8/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-017 | + | Jay 138 kV | IN | Jay | Active | AEP | 146.6 | 16.64 | 2.93 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1017_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1017_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/6/2020 | N/A | N/A | 9/30/2020 | N/A | N | No | ||||||||||||||||||
| AG1-017 | - | Jay 138 kV | IN | Jay | Active | AEP | 146.6 | 16.64 | 2.93 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1017_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/6/2020 | N/A | N/A | 9/30/2020 | N/A | N | No | ||||||||||||||||||||
| AG1-019 | + | Arnold’s Corner-Dahlgren 230 kV | VA | King George | Active | Dominion | 200 | 100 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1019_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1019_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/20/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-019 | - | Arnold’s Corner-Dahlgren 230 kV | VA | King George | Active | Dominion | 200 | 100 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1019_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/20/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-021 | + | Jetersville-Ponton 115 kV | VA | Amelia | Active | Dominion | 86 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1021_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1021_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||
| AG1-021 | - | Jetersville-Ponton 115 kV | VA | Amelia | Active | Dominion | 86 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1021_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-022 | + | Scottsville-Colleen 138 kV | VA | Albemarle | Active | AEP | 95 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1022_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1022_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||
| AG1-022 | - | Scottsville-Colleen 138 kV | VA | Albemarle | Active | AEP | 95 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1022_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-023 | + | North Anna-Louisa 230 kV | VA | Louisa | Active | Dominion | 75 | 75 | 15 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1023_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1023_imp.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-023 | - | North Anna-Louisa 230 kV | VA | Louisa | Active | Dominion | 75 | 75 | 15 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1023_fea.pdf | Document Posted | In Progress | N/A | N/A | 5/26/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-024 | + | Centerburg 138 kV | OH | Licking | Active | AEP | 285 | 85 | 35.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1024_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1024_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/1/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-024 | - | Centerburg 138 kV | OH | Licking | Active | AEP | 285 | 85 | 35.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1024_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/1/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-027 | + | Suffolk-Holland 115 kV | VA | City of Suffolk | Withdrawn | Dominion | 127.5 | 127.5 | 82.11 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1027_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1027_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 6/8/2020 | N/A | N/A | 9/27/2021 | 12/31/2024 | N/A | N | No | |||||||||||||||||
| AG1-027 | - | Suffolk-Holland 115 kV | VA | City of Suffolk | Active | Dominion | 127.5 | 127.5 | 82.11 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1027_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/8/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-028 | + | Suffolk-Holland 115 kV | VA | City of Suffolk | Withdrawn | Dominion | 127.5 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1028_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1028_imp.pdf | Document Posted | N/A | N/A | 6/8/2020 | N/A | N/A | 9/27/2021 | 12/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-028 | - | Suffolk-Holland 115 kV | VA | City of Suffolk | Active | Dominion | 127.5 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1028_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/8/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-029 | + | Weirton Solar 24 kV | WV | Hancock | Active | APS | 30 | 30 | 13.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1029_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1029_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/9/2020 | N/A | N/A | 11/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-029 | - | Weirton Solar 24 kV | WV | Hancock | Active | APS | 30 | 30 | 13.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1029_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/9/2020 | N/A | N/A | 11/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-031 | + | Elk Run D.P.-Gainesville 230 kV | VA | Fauquier | Active | Dominion | 90 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1031_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1031_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/10/2020 | N/A | N/A | 11/30/2021 | N/A | N | No | ||||||||||||||||||
| AG1-031 | - | Elk Run D.P.-Gainesville 230 kV | VA | Fauquier | Active | Dominion | 90 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1031_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1031_imp.pdf | Document Posted | N/A | N/A | 6/10/2020 | N/A | N/A | 11/30/2021 | N/A | N | No | |||||||||||||||||||
| AG1-033 | + | Scalp Level 23 kV | PA | Somerset | Withdrawn | PENELEC | 5 | 5 | 3.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1033_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1033_imp.pdf | Document Posted | N/A | N/A | 6/12/2020 | N/A | N/A | 9/16/2021 | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-033 | - | Scalp Level 23 kV | PA | Somerset | Active | PENELEC | 5 | 5 | 3.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1033_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/12/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-034 | + | Centerburg 138 kV | OH | Licking | Active | AEP | 127.5 | 127.5 | 53.55 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1034_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1034_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/12/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-034 | - | Centerburg 138 kV | OH | Licking | Active | AEP | 127.5 | 127.5 | 53.55 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1034_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/12/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-037 | + | Ahoskie 34.5 kV | NC | Hertford | Active | Dominion | 5 | 5 | 3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1037_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1037_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/16/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-037 | - | Ahoskie 34.5 kV | NC | Hertford | Active | Dominion | 5 | 5 | 3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1037_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1037_imp.pdf | Document Posted | N/A | N/A | 6/16/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||||||
| AG1-038 | + | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 176 | 45 | 18.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1038_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1038_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/16/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-038 | - | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 176 | 45 | 18.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1038_fea.pdf | Document Posted | N/A | N/A | 6/16/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | |||||||||||||||||||||
| AG1-039 | + | Galion 138 kV | OH | Morrow | Active | ATSI | 144 | 56 | 23.52 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1039_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1039_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-039 | - | Galion 138 kV | OH | Morrow | Active | ATSI | 144 | 56 | 23.52 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1039_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-040 | + | Morgan Street-Mount Hope 34.5 kV | PA | Crawford | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1040_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1040_imp.pdf | Document Posted | N/A | N/A | 6/19/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | |||||||||||||||||||
| AG1-040 | - | Morgan Street-Mount Hope 34.5 kV | PA | Crawford | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1040_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/19/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-041 | + | Osterburg-Bedford North 23 kV | PA | Bedford | Active | PENELEC | 12 | 12 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1041_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1041_imp.pdf | Document Posted | In Progress | N/A | N/A | 6/25/2020 | N/A | N/A | 12/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-041 | - | Osterburg-Bedford North 23 kV | PA | Bedford | Active | PENELEC | 12 | 12 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1041_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/25/2020 | N/A | N/A | 12/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-042 | + | Hayden 345 kV | OH | Franklin | Withdrawn | AEP | 100 | 100 | 66.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1042_fea.pdf | Document Posted | Withdrawn | N/A | N/A | 6/26/2020 | N/A | N/A | 8/19/2021 | 12/1/2023 | N/A | N | No | |||||||||||||||||||
| AG1-042 | - | Hayden 345 kV | OH | Franklin | Active | AEP | 100 | 100 | 66.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1042_fea.pdf | Document Posted | In Progress | N/A | N/A | 6/26/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-043 | + | Sowego 115 kV | VA | Accomack | Withdrawn | Dominion | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1043_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1043_imp.pdf | Document Posted | N/A | N/A | 6/26/2020 | N/A | N/A | 10/1/2021 | 12/12/2023 | N/A | N | No | ||||||||||||||||||
| AG1-043 | - | Sowego 115 kV | VA | Fauquier | Active | Dominion | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1043_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1043_imp.pdf | Document Posted | N/A | N/A | 6/26/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | |||||||||||||||||||
| AG1-044 | + | Whiteside County | Rock River ESS | IL | Whiteside | Under Construction | ComEd | 0.5 | 0.5 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1044_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1044_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1044_wmpa.pdf | Not Required | N/A | N/A | 7/1/2020 | N/A | N/A | 4/30/2021 | 7/30/2021 | 7/30/2021 | N/A | Y | No | ||||||||||
| AG1-044 | - | Whiteside County | Rock River ESS | IL | Whiteside | Engineering and Procurement | ComEd | 0.5 | 0.5 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1044_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1044_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1044_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1044_wmpa.pdf | Not Required | N/A | N/A | 7/1/2020 | N/A | N/A | 4/30/2021 | 7/30/2021 | 7/30/2021 | N/A | Y | No | ||||||||||
| AG1-045 | + | Redbud-Gaylord 34.5 kV | VA | Frederick | Active | APS | 36 | 36 | 18 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1045_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1045_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/2/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-045 | - | Redbud-Gaylord 34.5 kV | VA | Frederick | Active | APS | 36 | 36 | 18 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1045_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/2/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-047 | + | Jay 138 kV | IN | Jay | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1047_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1047_imp.pdf | Document Posted | N/A | N/A | 7/13/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | |||||||||||||||||||
| AG1-047 | - | Jay 138 kV | IN | Jay | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1047_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/13/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-049 | + | College Corner 138 kV | OH | Preble | Active | AEP | 80 | 0 | 17.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1049_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1049_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-049 | - | College Corner 138 kV | OH | Preble | Active | AEP | 80 | 0 | 17.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1049_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-050 | + | Milton 69 kV | PA | Northumberland | Active | PPL | 90 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1050_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1050_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-050 | - | Milton 69 kV | PA | Northumberland | Active | PPL | 90 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1050_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-051 | + | Maysville 69 kV III | PA | Mercer | Active | ATSI | 88 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1051_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1051_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-051 | - | Maysville 69 kV III | PA | Mercer | Active | ATSI | 88 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1051_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-052 | + | Zionsview-Middletown 115 kV II | PA | York | Active | ME | 99.6 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1052_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1052_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 9/30/2021 | N/A | N | No | ||||||||||||||||||
| AG1-052 | - | Zionsview-Middletown 115 kV II | PA | York | Active | ME | 99.6 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1052_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 9/30/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-054 | + | Potter-Harlan 69 kV | PA | Lawrence | Active | ATSI | 40 | 40 | 25.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1054_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1054_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/21/2020 | N/A | N/A | 5/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-054 | - | Potter-Harlan 69 kV | PA | Lawrence | Active | ATSI | 40 | 40 | 25.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1054_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/21/2020 | N/A | N/A | 5/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-057 | + | Harmony Village 230 kV | VA | Middlesex | Active | Dominion | 100 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1057_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1057_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/27/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-057 | - | Harmony Village 230 kV | VA | Middlesex | Active | Dominion | 100 | 20 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1057_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/27/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-059 | + | Robbins 138 kV | PA | Westmoreland | Active | APS | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1059_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1059_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/29/2020 | N/A | N/A | 1/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-059 | - | Robbins 138 kV | PA | Westmoreland | Active | APS | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1059_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/29/2020 | N/A | N/A | 1/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-060 | + | Eldred 69 kV | PA | Schuylkill | Active | PPL | 174.8 | 174.8 | 25.7 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1060_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1060_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/29/2020 | N/A | N/A | 5/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-060 | - | Eldred 69 kV | PA | Schuylkill | Active | PPL | 174.8 | 174.8 | 25.7 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1060_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/29/2020 | N/A | N/A | 5/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-061 | + | Laurel-Sharptown 69 kV | DE | Sussex | Active | DPL | 109.3 | 109.3 | 65.58 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1061_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1061_imp.pdf | Document Posted | N/A | N/A | 7/29/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||||||
| AG1-061 | - | Laurel-Sharptown 69 kV | DE | Sussex | Active | DPL | 109.3 | 109.3 | 65.58 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1061_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/29/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-066 | + | Bonnyman 69 kV | KY | Perry | Active | AEP | 80 | 80 | 48 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1066_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1066_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 10/2/2024 | N/A | N | No | ||||||||||||||||||
| AG1-066 | - | Bonnyman 69 kV | KY | Perry | Active | AEP | 80 | 80 | 48 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1066_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 10/2/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-067 | + | Temple Hill 69 kV | KY | Barren | Active | EKPC | 38 | 38 | 24.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1067_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1067_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-067 | - | Temple Hill 69 kV | KY | Barren | Active | EKPC | 38 | 38 | 24.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1067_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-068 | + | London-Tangy 69 kV | OH | Adams | Withdrawn | ATSI | 49.9 | 49.9 | 30.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1068_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1068_imp.pdf | Document Posted | N/A | N/A | 7/30/2020 | N/A | N/A | 10/4/2021 | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-068 | - | London-Tangy 69 kV | OH | Madison | Active | ATSI | 49.9 | 49.9 | 30.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1068_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-070 | + | Bon Ayr 69 kV | KY | Barren | Active | EKPC | 45 | 45 | 32.7 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1070_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1070_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-070 | - | Bon Ayr 69 kV | KY | Barren | Active | EKPC | 45 | 45 | 32.7 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1070_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-071 | + | Bon Ayr 69 kV | KY | Barren | Active | EKPC | 55 | 55 | 37.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1071_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1071_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-071 | - | Bon Ayr 69 kV | KY | Barren | Active | EKPC | 55 | 55 | 37.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1071_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-072 | + | Hillsboro-Steele 138 kV II | MD | Queen Anne’s | Withdrawn | DPL | 50 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1072_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1072_imp.pdf | Document Posted | N/A | N/A | 7/30/2020 | N/A | N/A | 9/28/2021 | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-072 | - | Hillsboro-Steele 138 kV II | MD | Queen Anne’s | Active | DPL | 150 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1072_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/30/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-076 | + | Fostoria Central 138 kV | OH | Hancock | Active | AEP | 205 | 0 | 46 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1076_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1076_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-076 | - | Fostoria Central 138 kV | OH | Hancock | Active | AEP | 205 | 0 | 46 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1076_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-077 | + | Allegheny Tunnel 23 kV | KY | Magoffin | Withdrawn | PENELEC | Energy | Generation Interconnection | Storage; Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1077_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1077_imp.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 9/21/2021 | 5/31/2022 | N/A | Y | No | |||||||||||||||||||||
| AG1-077 | - | Allegheny Tunnel 23 kV | PA | Adams | Active | PENELEC | 3.7 | 3.7 | 0 | Energy | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1077_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 5/31/2022 | N/A | Y | No | ||||||||||||||||||||
| AG1-080 | + | Delair-Locust Street 69 kV | NJ | Camden | Active | PSEG | 19.9 | 19.9 | 10.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1080_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1080_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/23/2022 | N/A | N | No | ||||||||||||||||||
| AG1-080 | - | Delair-Locust Street 69 kV | NJ | Camden | Active | PSEG | 19.9 | 19.9 | 10.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1080_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/23/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-084 | + | Earlys 34.5 kV | NC | Hertford | Withdrawn | Dominion | 17.5 | 17.5 | 10.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1084_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1084_imp.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 10/8/2021 | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-084 | - | Earlys 34.5 kV | NC | Hertford | Active | Dominion | 17.5 | 17.5 | 10.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1084_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-085 | + | Earlys 34.5 | NC | Hertford | Withdrawn | Dominion | 17.5 | 17.5 | 10.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1085_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1085_imp.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 10/8/2021 | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-085 | - | Earlys 34.5 | NC | Hertford | Active | Dominion | 17.5 | 17.5 | 10.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1085_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-087 | + | Milford-Cartanza 230 kV | DE | Sussex | Active | DPL | 440 | 440 | 119 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1087_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1087_imp.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 10/31/2026 | N/A | N | No | |||||||||||||||||||
| AG1-087 | - | Milford-Cartanza 230 kV | DE | Sussex | Active | DPL | 440 | 440 | 119 | Capacity | Generation Interconnection | Offshore Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1087_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 10/31/2026 | N/A | N | No | ||||||||||||||||||||
| AG1-088 | + | Carll’s Corner-Sherman Ave 69 kV | NJ | Cumberland | Active | AEC | 0 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1088_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1088_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-088 | - | Carll’s Corner-Sherman Ave 69 kV | NJ | Cumberland | Active | AEC | 0 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1088_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-089 | + | Grandview-Clifftop 138 kV | WV | N/A | Active | AEP | 120 | 30 | 12 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1089_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1089_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-089 | - | Grandview-Clifftop 138 kV | WV | N/A | Active | AEP | 120 | 30 | 12 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1089_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-091 | + | Hickman-River Bend 69 kV | VA | Pulaski | Active | AEP | 50 | 50 | 32.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1091_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1091_imp.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-091 | - | Hickman-River Bend 69 kV | VA | Pulaski | Active | AEP | 50 | 50 | 32.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1091_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-092 | + | Hickman-River Bend 69 kV | VA | Pulaski | Withdrawn | AEP | 50 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1092_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1092_imp.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 10/4/2021 | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-092 | - | Hickman-River Bend 69 kV | VA | Pulaski | Active | AEP | 50 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1092_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/31/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-094 | + | Burches Hill 230 kV | MD | Prince George’s | Active | PEPCO | 265.3 | 35.3 | 0 | Energy | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1094_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1094_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/7/2020 | N/A | N/A | 8/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-094 | - | Burches Hill 230 kV | MD | Prince George’s | Active | PEPCO | 265.3 | 35.3 | 0 | Energy | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1094_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/7/2020 | N/A | N/A | 8/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-096 | + | Rineyville 69 kV | KY | Hardin | Active | EKPC | 55 | 55 | 36.6667 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1096_fea.pdf | Document Posted | N/A | N/A | 8/14/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-096 | - | Rineyville 69 kV | KY | Hardin | Active | EKPC | 55 | 55 | 36.6667 | Capacity | Generation Interconnection | Solar; Storage | In Progress | N/A | N/A | 8/14/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-100 | + | Venango-Saegertown 34.5 kV | PA | Crawford | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1100_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1100_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/18/2020 | N/A | N/A | 12/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-100 | - | Venango-Saegertown 34.5 kV | PA | Crawford | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1100_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/18/2020 | N/A | N/A | 12/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-101 | + | Oakland-Gorman 69 kV | MD | Garrett | Active | APS | 20 | 10 | 6.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1101_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1101_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/20/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-101 | - | Oakland-Gorman 69 kV | MD | Garrett | Active | APS | 27 | 10 | 6.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1101_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1101_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/20/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-102 | + | White Marsh 34.5 kV | VA | Gloucester | Active | Dominion | 19 | 19 | 6.16 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1102_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1102_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/21/2020 | N/A | N/A | 7/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-102 | - | White Marsh 34.5 kV | VA | Gloucester | Active | Dominion | 19 | 19 | 6.16 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1102_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1102_imp.pdf | Document Posted | N/A | N/A | 8/21/2020 | N/A | N/A | 7/1/2022 | N/A | N | No | |||||||||||||||||||
| AG1-103 | + | Clayton-Williamstown 69 kV | NJ | Gloucester | Active | AEC | 44 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1103_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1103_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/24/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-103 | - | Clayton-Williamstown 69 kV | NJ | Gloucester | Active | AEC | 44 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1103_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/24/2020 | N/A | N/A | 6/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-104 | + | Waugh Chapel 230 kV | MD | Anne Arundel | Active | BGE | 300 | 300 | 120 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1104_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1104_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/25/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-104 | - | Waugh Chapel 230 kV | MD | Anne Arundel | Active | BGE | 300 | 300 | 120 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1104_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/25/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-107 | + | Hillsboro-Middleboro 138 kV | OH | Highland | Active | AEP | 200 | 150 | 85.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1107_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1107_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-107 | - | Hillsboro-Middleboro 138 kV | OH | Highland | Active | AEP | 200 | 150 | 85.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1107_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-109 | + | Valley 138 kV | MI | Van Buren | Active | AEP | 50 | 0 | 25 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1109_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1109_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-109 | - | Valley 138 kV | MI | Van Buren | Active | AEP | 50 | 0 | 25 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1109_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-110 | + | Silver Lake 69 kV | NJ | Camden | Active | AEC | 40 | 0 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1110_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1110_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 11/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-110 | - | Silver Lake 69 kV | NJ | Camden | Active | AEC | 40 | 0 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1110_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 11/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-115 | + | Buxmont 69 kV | PA | Bucks | Active | PPL | 200 | 0 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1115_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1115_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 11/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-115 | - | Buxmont 69 kV | PA | Bucks | Active | PPL | 200 | 0 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1115_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 11/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-116 | + | Newport-South Millville 69 kV | NJ | Cumberland | Active | AEC | 59.7 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1116_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1116_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/3/2021 | N/A | N | No | ||||||||||||||||||
| AG1-116 | - | Newport-South Millville 69 kV | NJ | Cumberland | Active | AEC | 59.7 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1116_fea.pdf | Document Posted | N/A | N/A | 8/31/2020 | N/A | N/A | 12/3/2021 | N/A | N | No | |||||||||||||||||||||
| AG1-117 | + | Churchtown-Upper Pittsgrove 138 kV | NJ | Salem | Active | AEC | 149.3 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1117_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1117_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/3/2021 | N/A | N | No | ||||||||||||||||||
| AG1-117 | - | Churchtown-Upper Pittsgrove 138 kV | NJ | Salem | Active | AEC | 149.3 | 0 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1117_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/3/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-123 | + | Amherst-Riverville138 kV | VA | Amherst | Active | AEP | 75 | 75 | 44.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1123_fea.pdf | Document Posted | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-123 | - | Amherst-Riverville138 kV | VA | Amherst | Active | AEP | 75 | 75 | 44.2 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||||
| AG1-125 | + | Marysville-Flatlick 765 kV | OH | Madison | Active | AEP | 400 | 400 | 234.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1125_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1125_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-125 | - | Marysville-Flatlick 765 kV | OH | Madison | Active | AEP | 400 | 400 | 234.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1125_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-126 | + | Marysville-Flatlick 765 kV | OH | Madison | Active | AEP | 400 | 400 | 234.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1126_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1126_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-126 | - | Marysville-Flatlick 765 kV | OH | Madison | Active | AEP | 400 | 400 | 234.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1126_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-129 | + | US Silica - Unimin 69 kV | NJ | Atlantic | Withdrawn | AEC | 51 | 51 | 30.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1129_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1129_imp.pdf | Document Posted | N/A | N/A | 8/31/2020 | N/A | N/A | 10/1/2021 | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-129 | - | US Silica - Unimin 69 kV | NJ | Cumberland | Active | AEC | 51 | 51 | 30.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1129_fea.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-130 | + | Burlington 26 kV | NAES | NJ | Burlington | Engineering and Procurement | PSEG | 5 | 5 | 2 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1130_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1130_imp.pdf | Document Posted | Not Required | https://www.pjm.com/pub/planning/project-queues/isa/ag1_130_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ag1_130_csa.pdf | Document Posted | N/A | N/A | 8/31/2020 | N/A | N/A | 2/28/2023 | 2/28/2023 | N/A | N | No | |||||||||||
| AG1-130 | - | Burlington 26 kV | NJ | Burlington | Active | PSEG | 5 | 5 | 2 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1130_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1130_imp.pdf | Document Posted | In Progress | N/A | N/A | 8/31/2020 | N/A | N/A | 12/28/2022 | N/A | N | No | ||||||||||||||||||
| AG1-131 | + | Edinburg 115 kV | VA | Shenandoah | Active | Dominion | 25.6 | 25.6 | 15.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1131_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1131_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-131 | - | Edinburg 115 kV | VA | Shenandoah | Active | Dominion | 25.6 | 25.6 | 15.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1131_fea.pdf | Document Posted | N/A | N/A | 9/2/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | |||||||||||||||||||||
| AG1-132 | + | Tait 69 kV | OH | Montgomery | Active | Dayton | 606 | 20 | 20 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1132_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1132_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 6/1/2021 | N/A | N | No | ||||||||||||||||||
| AG1-132 | - | Tait 69 kV | OH | Montgomery | Active | Dayton | 606 | 20 | 20 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1132_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 6/1/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-133 | + | North Anna-Ladysmith 500 kV | VA | Spotsylvania | Active | Dominion | 128 | 128 | 76.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1133_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1133_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-133 | - | North Anna-Ladysmith 500 kV | VA | Spotsylvania | Active | Dominion | 128 | 128 | 76.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1133_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-134 | + | Kings Dominion DP 115 kV | VA | King William | Active | Dominion | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1134_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1134_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-134 | - | Kings Dominion DP 115 kV | VA | King William | Active | Dominion | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1134_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/2/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-135 | + | Garner-Lancaster 115 kV | VA | Richmond | Active | Dominion | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1135_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1135_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/3/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-135 | - | Garner-Lancaster 115 kV | VA | Richmond | Active | Dominion | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1135_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/3/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-136 | + | Cloverdale-Burlington Height 138 kV | VA | Botetourt | Active | AEP | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1136_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1136_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/3/2020 | N/A | N/A | 10/22/2023 | N/A | N | No | ||||||||||||||||||
| AG1-136 | - | Cloverdale-Burlington Height 138 kV | VA | Botetourt | Active | AEP | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1136_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/3/2020 | N/A | N/A | 10/22/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-137 | + | Harrisonburg 230 kV | VA | Rockingham | Withdrawn | Dominion | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1137_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1137_imp.pdf | Document Posted | N/A | N/A | 9/3/2020 | N/A | N/A | 9/13/2021 | 10/22/2023 | N/A | N | No | ||||||||||||||||||
| AG1-137 | - | Harrisonburg 230 kV | VA | Rockingham | Active | Dominion | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1137_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/3/2020 | N/A | N/A | 10/22/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-138 | + | Wolfs Corners 34.5 kV | PA | Clarion | Withdrawn | PENELEC | 25 | 5 | 4.75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1138_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1138_imp.pdf | Document Posted | N/A | N/A | 9/4/2020 | N/A | N/A | 11/1/2021 | 9/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-138 | - | Wolfs Corners 34.5 kV | PA | Clarion | Active | PENELEC | 25 | 5 | 4.75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1138_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/4/2020 | N/A | N/A | 9/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-139 | + | Clark Summit-Emlenton 34.5 kV | PA | Venango | Withdrawn | PENELEC | 25 | 5 | 4.75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1139_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1139_imp.pdf | Document Posted | N/A | N/A | 9/4/2020 | N/A | N/A | 11/1/2021 | 9/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-139 | - | Clark Summit-Emlenton 34.5 kV | PA | Venango | Active | PENELEC | 25 | 5 | 4.75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1139_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/4/2020 | N/A | N/A | 9/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-141 | + | Hempfield 12.47 kV | Hempfield CSG 1 | PA | Westmoreland | Suspended | APS | 5 | 5 | 2.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1141_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1141_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1141_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1141_wmpa.pdf | Not Required | N/A | N/A | 9/3/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | N | No | |||||||||||
| AG1-141 | - | Hempfield 12.47 kV | Hempfield CSG 1 | PA | Westmoreland | Engineering and Procurement | APS | 5 | 5 | 2.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1141_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1141_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1141_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1141_wmpa.pdf | Not Required | N/A | N/A | 9/3/2020 | N/A | N/A | 9/30/2022 | 9/30/2022 | N/A | N | No | |||||||||||
| AG1-143 | + | Gainesville-Loudoun 230 kV | VA | Prince William | Active | Dominion | 200 | 200 | 80 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1143_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1143_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/4/2020 | N/A | N/A | 10/22/2023 | N/A | N | No | ||||||||||||||||||
| AG1-143 | - | Gainesville-Loudoun 230 kV | VA | Prince William | Active | Dominion | 200 | 200 | 80 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1143_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/4/2020 | N/A | N/A | 10/22/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-146 | + | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 30 | 30 | 18 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1146_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1146_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-146 | - | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 30 | 30 | 18 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1146_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-147 | + | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 70 | 70 | 42 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1147_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1147_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-147 | - | Garner DP-Lancaster 115 kV | VA | Lancaster | Active | Dominion | 70 | 70 | 42 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1147_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-150 | + | Wattsville 69 kV II | VA | Accomack | Active | DPL | 80 | 40 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1150_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1150_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||
| AG1-150 | - | Wattsville 69 kV II | VA | Accomack | Active | DPL | 80 | 40 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1150_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 12/1/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-151 | + | Endless Caverns 115 kV | VA | Rockingham | Active | Dominion | 300 | 100 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1151_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1151_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 10/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-151 | - | Endless Caverns 115 kV | VA | Rockingham | Active | Dominion | 300 | 100 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1151_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/9/2020 | N/A | N/A | 10/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-152 | + | Remington CT 230 kV | VA | Fauquier | Active | Dominion | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1152_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1152_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-152 | - | Remington CT 230 kV | VA | Fauquier | Active | Dominion | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1152_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1152_imp.pdf | Document Posted | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | |||||||||||||||||||
| AG1-153 | + | Heritage 500 kV | VA | Brunswick | Active | Dominion | 75 | 75 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1153_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1153_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-153 | - | Heritage 500 kV | VA | Brunswick | Active | Dominion | 75 | 75 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1153_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-154 | + | Ladysmith CT 230 kV | VA | Caroline | Active | Dominion | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1154_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1154_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-154 | - | Ladysmith CT 230 kV | VA | Caroline | Active | Dominion | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1154_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-156 | + | Jack Frost-Lake Harmony 69 kV | PA | Carbon | Active | PPL | 60 | 60 | 39.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1156_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1156_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 6/15/2024 | N/A | N | No | ||||||||||||||||||
| AG1-156 | - | Jack Frost-Lake Harmony 69 kV | PA | Carbon | Active | PPL | 60 | 60 | 39.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1156_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/10/2020 | N/A | N/A | 6/15/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-157 | + | Macungie-Emmaus Tie 69 kV | PA | Lehigh | Active | PPL | 7.4 | 7.37 | 0 | Energy | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1157_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1157_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/11/2020 | N/A | N/A | 6/16/2022 | N/A | N | No | ||||||||||||||||||
| AG1-157 | - | Macungie-Emmaus Tie 69 kV | PA | Lehigh | Active | PPL | 7.4 | 7.37 | 0 | Energy | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1157_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/11/2020 | N/A | N/A | 6/16/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-160 | + | Rogers Road 500 kV | VA | Greensville | Active | Dominion | 75 | 75 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1160_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1160_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/11/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-160 | - | Rogers Road 500 kV | VA | Greensville | Active | Dominion | 75 | 75 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1160_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/11/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-162 | + | Sporn 138 kV | WV | Mason | Active | AEP | 33.4 | 33.4 | 17.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1162_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1162_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/14/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-162 | - | Sporn 138 kV | WV | Mason | Active | AEP | 33.4 | 33.4 | 17.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1162_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/14/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-164 | + | East Hazelton-Weatherly Tap 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1164_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1164_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 8/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-164 | - | East Hazelton-Weatherly Tap 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1164_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 8/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-165 | + | East Hazelton-Weatherly Tap 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1165_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1165_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 5/15/2022 | N/A | N | No | ||||||||||||||||||
| AG1-165 | - | East Hazelton-Weatherly Tap 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1165_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 5/15/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-166 | + | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1166_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1166_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-166 | - | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1166_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-167 | + | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1167_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1167_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-167 | - | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1167_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-168 | + | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1168_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1168_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-168 | - | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1168_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-169 | + | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1169_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1169_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-169 | - | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1169_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-170 | + | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1170_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1170_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||
| AG1-170 | - | Lone Pine 115 kV | VA | Nottoway | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1170_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/16/2020 | N/A | N/A | 10/15/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-180 | + | Brunswick-Gasburg 69 kV | VA | Sussex | Active | Dominion | 50 | 0 | 16.4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1180_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-180 | - | Brunswick-Gasburg 69 kV | VA | Sussex | Active | Dominion | 50 | 0 | 16.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1180_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-182 | + | Millville-Old Chapel 138 kV | VA | Clarke | Active | APS | 100 | 100 | 65.21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1182_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1182_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-182 | - | Millville-Old Chapel 138 kV | VA | Clarke | Active | APS | 100 | 100 | 65.21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1182_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-183 | + | St. Johns DP-REC 115 kV | VA | King and Queen | Withdrawn | Dominion | 50 | 50 | 35.52 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1183_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1183_imp.pdf | Document Posted | N/A | N/A | 9/17/2020 | N/A | N/A | 9/1/2021 | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-183 | - | St. Johns DP-REC 115 kV | VA | King and Queen | Active | Dominion | 50 | 50 | 35.52 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1183_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-184 | + | Carson-Suffolk 500 kV | VA | Sussex | Active | Dominion | 500 | 0 | 175.06 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1184_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-184 | - | Carson-Suffolk 500 kV | VA | Sussex | Active | Dominion | 500 | 0 | 175.06 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1184_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-186 | + | Millville-Old Chapel 138 kV | VA | Clarke | Active | APS | 100 | 0 | 34.79 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1186_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1186_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-186 | - | Millville-Old Chapel 138 kV | VA | Clarke | Active | APS | 100 | 0 | 34.79 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1186_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-187 | + | St. Johns DP-REC 115 kV | VA | King and Queen | Withdrawn | Dominion | 50 | 0 | 14.48 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1187_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1187_imp.pdf | Document Posted | N/A | N/A | 9/17/2020 | N/A | N/A | 9/1/2021 | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-187 | - | St. Johns DP-REC 115 kV | VA | King and Queen | Active | Dominion | 50 | 0 | 14.48 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1187_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-191 | + | Chester-Pohatcong Mountain 34.5 kV | NJ | Morris | Active | JCPL | 15.4 | 15.4 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1191_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1191_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||
| AG1-191 | - | Chester-Pohatcong Mountain 34.5 kV | NJ | Morris | Active | JCPL | 15.4 | 15.4 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1191_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-193 | + | Utica Junction 34.5 kV | PA | Venango | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1193_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1193_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-193 | - | Utica Junction 34.5 kV | PA | Venango | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1193_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/17/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-194 | + | Nuttall 138 kV | WV | Fayette | Active | AEP | 200 | 200 | 104 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1194_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1194_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-194 | - | Nuttall 138 kV | WV | Fayette | Active | AEP | 200 | 200 | 104 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1194_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-195 | + | Valley 230 kV | VA | Augusta | Active | Dominion | 150 | 150 | 150 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1195_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1195_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-195 | - | Valley 230 kV | VA | Augusta | Active | Dominion | 150 | 150 | 150 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1195_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-196 | + | Grottoes 115 kV | VA | Augusta | Active | Dominion | 150 | 150 | 150 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1196_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1196_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-196 | - | Grottoes 115 kV | VA | Augusta | Active | Dominion | 150 | 150 | 150 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1196_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-197 | + | Morgan Street-Cochranton 34.5 kV | PA | Crawford | Active | PENELEC | 15 | 15 | 9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1197_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1197_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-197 | - | Morgan Street-Cochranton 34.5 kV | PA | Crawford | Active | PENELEC | 15 | 15 | 9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1197_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-198 | + | Union City 34.5 kV | PA | Erie | Active | PENELEC | 12 | 12 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1198_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1198_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-198 | - | Union City 34.5 kV | PA | Erie | Active | PENELEC | 12 | 12 | 7.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1198_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/18/2020 | N/A | N/A | 1/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-202 | + | Springboro 12.47 kV | PA | Crawford | Active | PENELEC | 10 | 10 | 6.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1202_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1202_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-202 | - | Springboro 12.47 kV | PA | Crawford | Active | PENELEC | 10 | 10 | 6.6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1202_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-203 | + | Reels Corner 23 kV | PA | Somerset | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1203_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1203_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-203 | - | Reels Corner 23 kV | PA | Somerset | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1203_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-205 | + | Rockwood 23 kV | PA | Somerset | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1205_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1205_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-205 | - | Rockwood 23 kV | PA | Somerset | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1205_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-207 | + | Vandalia 69 kV | OH | Montgomery | Active | Dayton | 85 | 85 | 85 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1207_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1207_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-207 | - | Vandalia 69 kV | OH | Montgomery | Active | Dayton | 85 | 85 | 85 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1207_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-209 | + | Gretna 12.5 kV | VA | Pittsylvania | Active | Dominion | 7 | 7 | 2.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1209_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1209_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-209 | - | Gretna 12.5 kV | VA | Pittsylvania | Active | Dominion | 7 | 7 | 2.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1209_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-210 | + | Northern Neck 34.5 kV | VA | Richmond | Active | Dominion | 10 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1210_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1210_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-210 | - | Northern Neck 34.5 kV | VA | Richmond | Active | Dominion | 10 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1210_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1210_imp.pdf | Document Posted | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | |||||||||||||||||||
| AG1-213 | + | St Johns 13.2 kV | Poplar Energy Storage | VA | Caroline | Engineering and Procurement | Dominion | 10 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1213_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1213_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1213_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1213_wmpa.pdf | Not Required | N/A | N/A | 9/22/2020 | N/A | N/A | 6/30/2024 | 6/30/2024 | N/A | N | No | |||||||||||
| AG1-213 | - | St Johns 13.2 kV | VA | Caroline | Active | Dominion | 10 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1213_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-214 | + | Grottoes 12.5 kV | VA | Rockingham | Active | Dominion | 19 | 19 | 7.6 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1214_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1214_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-214 | - | Grottoes 12.5 kV | VA | Rockingham | Active | Dominion | 19 | 19 | 7.6 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1214_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-215 | + | Fort Pickett 13.2 kV | VA | Nottoway | Active | Dominion | 14 | 14 | 5.6 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1215_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1215_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | ||||||||||||||||||
| AG1-215 | - | Fort Pickett 13.2 kV | VA | Nottoway | Active | Dominion | 14 | 14 | 5.6 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1215_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 12/30/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-217 | + | Cent Hardin-Kargle 69 kV Upgrade | KY | Unknown | Active | EKPC | Energy | Merchant Transmission | Not Required | https://www.pjm.com/pub/planning/project-queues/arr-impact-studies/ag1217_arr-imp.pdf | Document Posted | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||
| AG1-217 | - | Cent Hardin-Kargle 69 kV Upgrade | KY | Unknown | Active | EKPC | Energy | Merchant Transmission | Not Required | In Progress | N/A | N/A | 9/22/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||||
| AG1-218 | + | Marysville-Tangy 345 kV | OH | Union | Active | AEP | 250 | 250 | 150 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1218_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1218_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 3/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-218 | - | Marysville-Tangy 345 kV | OH | Union | Active | AEP | 250 | 250 | 150 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1218_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 3/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-219 | + | Layland 69 kV | WV | Fayette | Active | AEP | 75 | 75 | 39.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1219_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1219_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-219 | - | Layland 69 kV | WV | Fayette | Active | AEP | 75 | 75 | 39.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1219_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-221 | + | Poland Rd-Runway DP 230 kV | VA | Loudoun | Active | Dominion | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1221_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1221_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-221 | - | Poland Rd-Runway DP 230 kV | VA | Loudoun | Active | Dominion | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1221_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1221_imp.pdf | Document Posted | N/A | N/A | 9/23/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | |||||||||||||||||||
| AG1-222 | + | Guardian-Twin Branch 138 kV | IN | Elkhart | Active | AEP | 302.2 | 150 | 90 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1222_fea.pdf | Document Posted | N/A | N/A | 9/23/2020 | N/A | N/A | 5/31/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-222 | - | Guardian-Twin Branch 138 kV | IN | Elkhart | Active | AEP | 302.2 | 150 | 90 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 5/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-223 | + | Larrabee-Allaire 34.5 kV | NJ | Monmouth | Active | JCPL | 15.4 | 15.4 | 6.47 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1223_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1223_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-223 | - | Larrabee-Allaire 34.5 kV | NJ | Monmouth | Active | JCPL | 15.4 | 15.4 | 6.47 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1223_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/23/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-227 | + | Altamont-Tuscarora 69 kV | PA | Schuylkill | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1227_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1227_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/24/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-227 | - | Altamont-Tuscarora 69 kV | PA | Schuylkill | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1227_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/24/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-228 | + | Alta Haute-Tuscarora 69 kV | PA | Schuylkill | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1228_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1228_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/24/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-228 | - | Alta Haute-Tuscarora 69 kV | PA | Schuylkill | Active | PPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1228_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/24/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-231 | + | Glady Run–Xenia 69 kV | OH | Greene | Active | Dayton | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1231_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1231_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 3/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-231 | - | Glady Run–Xenia 69 kV | OH | Greene | Active | Dayton | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1231_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 3/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-232 | + | Magley 138 kV | IN | Adams | Active | AEP | 135 | 135 | 81 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1232_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1232_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-232 | - | Magley 138 kV | IN | Adams | Active | AEP | 135 | 135 | 81 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1232_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-237 | + | Dequine-Eugene 345 kV | IN | N/A | Active | AEP | 200 | 200 | 26 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1237_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1237_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-237 | - | Dequine-Eugene 345 kV | IN | N/A | Active | AEP | 200 | 200 | 26 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1237_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-239 | + | Blue Bell-South East Canton 138 kV | OH | Stark | Active | ATSI | 150 | 150 | 90 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1239_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1239_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 3/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-239 | - | Blue Bell-South East Canton 138 kV | OH | Stark | Active | ATSI | 150 | 150 | 90 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1239_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 3/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-246 | + | Gates Hill-Luzerne 25 kV | PA | Fayette | Active | APS | 7.5 | 7.5 | 4.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1246_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1246_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-246 | - | Gates Hill-Luzerne 25 kV | PA | Fayette | Active | APS | 7.5 | 7.5 | 4.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1246_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-248 | + | York Storage 115 kV | PA | York | Active | ME | 170 | 119 | 4.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1248_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-248 | - | York Storage 115 kV | PA | York | Active | ME | 200 | 149 | 13.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1248_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-251 | + | McDowell 12.47 kV | PA | Delaware | Active | ATSI | 3.9 | 3.88 | 1.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1251_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1251_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-251 | - | McDowell 12.47 kV | PA | Delaware | Active | ATSI | 3.9 | 3.88 | 1.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1251_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-254 | + | Salem-Woodstown 69 kV | NJ | Atlantic | Active | AEC | 38 | 38 | 25.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1254_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1254_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-254 | - | Salem-Woodstown 69 kV | NJ | Salem | Active | AEC | 70 | 70 | 46.6667 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1254_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-255 | + | Churchtown-Quinton 69 kV | NJ | Salem | Active | AEC | 55 | 55 | 36.7 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1255_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1255_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-255 | - | Churchtown-Orchard 230 kV | NJ | Salem | Active | AEC | 150 | 55 | 36.7 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1255_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/25/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-256 | + | Northern Neck 230 kV | VA | Accomack | Withdrawn | Dominion | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1256_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1256_imp.pdf | Document Posted | N/A | N/A | 9/28/2020 | N/A | N/A | 10/5/2021 | 1/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-256 | - | Northern Neck 230 kV | VA | Richmond | Active | Dominion | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1256_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 1/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-257 | + | Madisonburg Jct-Millheim 46 kV | PA | Centre | Active | APS | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1257_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1257_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-257 | - | Madisonburg Jct-Millheim 46 kV | PA | Centre | Active | APS | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1257_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-259 | + | Sunbury-Dalmatia 69 kV | PA | Northumberland | Active | PPL | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1259_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1259_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-259 | - | Sunbury-Dalmatia 69 kV | PA | Northumberland | Active | PPL | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1259_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-260 | + | Sunbury-Dalmatia 69 kV | PA | Northumberland | Active | PPL | 39.8 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1260_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1260_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-260 | - | Sunbury-Dalmatia 69 kV | PA | Northumberland | Active | PPL | 39.8 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1260_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 8/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-262 | + | Lower Mount Bethel 230 kV | PA | Northampton | Active | PPL | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1262_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-262 | - | Lower Mount Bethel 230 kV | PA | Northampton | Active | PPL | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||||||
| AG1-263 | + | Gloucester 230 kV | NJ | Camden | Active | PSEG | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1263_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1263_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-263 | - | Gloucester 230 kV | NJ | Camden | Active | PSEG | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1263_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1263_imp.pdf | Document Posted | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | |||||||||||||||||||
| AG1-267 | + | Martins Creek 69 kV | PA | Northampton | Active | PPL | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1267_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1267_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-267 | - | Martins Creek 69 kV | PA | Northampton | Active | PPL | 20 | 20 | 8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1267_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-268 | + | Essex 230 kV | NJ | Essex | Active | PSEG | 80 | 80 | 40.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1268_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1268_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-268 | - | Essex 230 kV | NJ | Essex | Active | PSEG | 80 | 80 | 40.8 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1268_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1268_imp.pdf | Document Posted | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2022 | N/A | N | No | |||||||||||||||||||
| AG1-277 | + | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 40 | 40 | 32 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1277_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1277_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-277 | - | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 40 | 40 | 32 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1277_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-278 | + | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 15.42 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1278_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1278_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-278 | - | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 15.42 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1278_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-279 | + | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 15.42 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1279_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1279_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-279 | - | Salem-Beacon Power 69 kV | PA | Luzerne | Active | PPL | 20 | 20 | 15.42 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1279_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-280 | + | Claysburg-Puzzletown 46 kV | PA | Blair | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1280_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1280_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-280 | - | Claysburg-Puzzletown 46 kV | PA | Blair | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1280_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-281 | + | Claysburg-HCR Tap 46 kV | PA | Blair | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1281_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1281_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-281 | - | Claysburg-HCR Tap 46 kV | PA | Blair | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1281_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-282 | + | Dunnsville 34.5 kV | VA | Essex | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1282_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1282_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-282 | - | Dunnsville 34.5 kV | VA | Essex | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1282_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-283 | + | Effort Mountain-Gilbert 138 kV | PA | Monroe | Active | PPL | 30 | 30 | 18 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1283_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1283_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 9/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-283 | - | Effort Mountain-Gilbert 138 kV | PA | Monroe | Active | PPL | 30 | 30 | 18 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1283_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 9/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-289 | + | Lake of the Woods DP-Wilderness DP 115 kV | VA | Orange | Active | Dominion | 150 | 0 | 53.41 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1289_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-289 | - | Lake of the Woods DP-Wilderness DP 115 kV | VA | Orange | Active | Dominion | 150 | 0 | 53.41 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1289_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-290 | + | Wagner 115 kV | MD | Baltimore County | Active | BGE | 20 | 20 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1290_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1290_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-290 | - | Wagner 115 kV | MD | Baltimore County | Active | BGE | 20 | 20 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1290_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 10/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-291 | + | Neville 23 kV | PA | Allegheny | Active | DL | 16.8 | 16.8 | 13.5 | Capacity | Generation Interconnection | Hydro | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1291_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1291_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/28/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-291 | - | Neville 23 kV | PA | Allegheny | Active | DL | 16.8 | 16.8 | 13.5 | Capacity | Generation Interconnection | Hydro | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1291_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1291_imp.pdf | Document Posted | N/A | N/A | 9/28/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | |||||||||||||||||||
| AG1-296 | + | Snyder Township 34.5 kV | PA | Jefferson | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1296_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1296_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-296 | - | Snyder Township 34.5 kV | PA | Jefferson | Active | PENELEC | 10 | 10 | 6.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1296_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-299 | + | U.S. Silica 12.47 kV | NJ | Atlantic | Withdrawn | AEC | 3 | 3 | 1.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1299_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1299_imp.pdf | Document Posted | N/A | N/A | 9/29/2020 | N/A | N/A | 10/1/2021 | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-299 | - | U.S. Silica 12.47 kV | NJ | Cumberland | Active | AEC | 3 | 3 | 1.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1299_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-300 | + | U.S Silica II 12.47 kV | NJ | Cumberland | Withdrawn | AEC | 3 | 3 | 1.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1300_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1300_imp.pdf | Document Posted | N/A | N/A | 9/29/2020 | N/A | N/A | 10/1/2021 | 12/31/2021 | N/A | N | No | ||||||||||||||||||
| AG1-300 | - | U.S Silica II 12.47 kV | NJ | Cumberland | Active | AEC | 5 | 5 | 3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1300_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-303 | + | Geneva 115 kV | PA | Crawford | Active | PENELEC | 44 | 44 | 26.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1303_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1303_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 9/25/2023 | N/A | N | No | ||||||||||||||||||
| AG1-303 | - | Geneva 115 kV | PA | Crawford | Active | PENELEC | 44 | 44 | 26.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1303_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 9/25/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-305 | + | Louisa-North Anna 230 kV | VA | Louisa | Active | Dominion | 118 | 118 | 70.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1305_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1305_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 7/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-305 | - | Louisa-North Anna 230 kV | VA | Louisa | Active | Dominion | 118 | 118 | 70.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1305_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 7/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-307 | + | Old Chapel-Millville 138 kV | WV | Jefferson | Active | APS | 80 | 80 | 56 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1307_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1307_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-307 | - | Old Chapel-Millville 138 kV | WV | Jefferson | Active | APS | 80 | 80 | 56 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1307_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-308 | + | Shawville-Philipsburg 34.5 kV | PA | Clearfield | Active | PENELEC | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1308_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1308_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-308 | - | Shawville-Philipsburg 34.5 kV | PA | Clearfield | Active | PENELEC | 19.9 | 19.9 | 8.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1308_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 8/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-311 | + | Apple Grove 138 kV | WV | Mason | Active | AEP | 99 | 99 | 69.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1311_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1311_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-311 | - | Apple Grove 138 kV | WV | Mason | Active | AEP | 99 | 99 | 69.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1311_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/29/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-315 | + | Lardin-Grays Landing 12.47 kV | Woodside Solar | PA | Fayette | Engineering and Procurement | APS | 2 | 2 | 0.84 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1315_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1315_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1315_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1315_wmpa.pdf | Not Required | N/A | N/A | 9/29/2020 | N/A | N/A | 9/30/2023 | 9/30/2023 | N/A | N | No | |||||||||||
| AG1-315 | - | Lardin-Grays Landing 12.47 kV | PA | Fayette | Active | APS | 2 | 2 | 0.84 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1315_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1315_imp.pdf | Document Posted | Not Required | Not Required | N/A | N/A | 9/29/2020 | N/A | N/A | 12/31/2021 | N/A | N | No | |||||||||||||||||
| AG1-322 | + | Birchwood 230 kV | VA | Accomack | Withdrawn | Dominion | 70 | 70 | 70 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1322_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1322_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2021 | 9/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-322 | - | Birchwood 230 kV | VA | King George | Active | Dominion | 70 | 70 | 70 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1322_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-323 | + | Blue Jacket 138 kV | OH | Logan | Active | Dayton | 40 | 40 | 40 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1323_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1323_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-323 | - | Blue Jacket 138 kV | OH | Logan | Active | Dayton | 40 | 40 | 40 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1323_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-324 | + | Jay-Desoto 138 kV | IN | Jay | Active | AEP | 45 | 45 | 31.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1324_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1324_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-324 | - | Jay-Desoto 138 kV | IN | Jay | Active | AEP | 45 | 45 | 31.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1324_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-327 | + | Ringgold – East Waynesboro 138 kV | PA | Franklin | Withdrawn | APS | 35 | 35 | 23.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1327_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1327_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 11/1/2021 | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-327 | - | Ringgold – East Waynesboro 138 kV | PA | Franklin | Active | APS | 35 | 35 | 23.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1327_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-330 | + | Beavertown 12.47 kV | ASD Brick Plant PA2 Solar | PA | Beaver | Engineering and Procurement | PPL | 5 | 5 | 4.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1330_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1330_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1330_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1330_wmpa.pdf | Not Required | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2024 | 3/1/2024 | N/A | N | No | |||||||||||
| AG1-330 | - | Beavertown 12.47 kV | ASD Brick Plant PA2 Solar | PA | Beaver | Engineering and Procurement | PPL | 5 | 5 | 4.5 | Capacity | Generation Interconnection | Solar; Battery | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1330_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1330_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1330_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1330_wmpa.pdf | Not Required | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2024 | 3/1/2024 | N/A | N | No | |||||||||||
| AG1-331 | + | Conneaut-Conneaut Tap 69 kV | PA | Crawford | Withdrawn | ATSI | 5 | 5 | 4.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1331_fea.pdf | Document Posted | Withdrawn | N/A | N/A | 9/30/2020 | N/A | N/A | 8/27/2021 | 7/31/2022 | N/A | N | No | |||||||||||||||||||
| AG1-331 | - | Conneaut-Conneaut Tap 69 kV | PA | Crawford | Active | ATSI | 5 | 5 | 4.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1331_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 7/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-338 | + | Curryville-RKB-Yellow Creek 23 kV I | PA | Bedford | Withdrawn | PENELEC | 5 | 5 | 4.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1338_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1338_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/9/2021 | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-338 | - | Curryville-RKB-Yellow Creek 23 kV I | PA | Bedford | Active | PENELEC | 5 | 5 | 4.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1338_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-340 | + | Curryville 23 kV | PA | Bedford | Withdrawn | PENELEC | 5 | 5 | 3.2 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1340_fea.pdf | Document Posted | Withdrawn | N/A | N/A | 9/30/2020 | N/A | N/A | 8/27/2021 | 6/30/2024 | N/A | N | No | |||||||||||||||||||
| AG1-340 | - | Curryville 23 kV | PA | Bedford | Active | PENELEC | 5 | 5 | 3.2 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1340_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-345 | + | Crewe 12.5 kV | VA | Nottoway | Withdrawn | Dominion | 8 | 8 | 4.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1345_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1345_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 10/8/2021 | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-345 | - | Crewe 12.5 kV | VA | Nottoway | Active | Dominion | 8 | 8 | 4.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1345_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-348 | + | Pequest River-Washington 34.5 kV | NJ | Warren | Active | JCPL | 19.8 | 19.8 | 8.316 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1348_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1348_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||
| AG1-348 | - | Pequest River-Washington 34.5 kV | NJ | Warren | Active | JCPL | 19.8 | 19.8 | 8.316 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1348_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-349 | + | Olive-Reynolds #2 345 kV | IN | Pulaski | Active | AEP | 260 | 260 | 156 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1349_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1349_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-349 | - | Olive-Reynolds #2 345 kV | IN | Pulaski | Active | AEP | 260 | 260 | 156 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1349_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-351 | + | Harrison-Good Hope 138 kV | OH | Fairfield | Active | AEP | 142 | 58 | 34.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1351_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-351 | - | Harrison-Good Hope 138 kV | OH | Fairfield | Active | AEP | 142 | 58 | 34.8 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-352 | + | Hunt Farm Junction 69 kV | KY | Boyle | Withdrawn | EKPC | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1352_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1352_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/28/2021 | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-352 | - | Hunt Farm Junction 69 kV | KY | Boyle | Active | EKPC | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1352_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-358 | + | Howard-Melmore 138 kV | OH | Crawford | Active | AEP | 58 | 58 | 34.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1358_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-358 | - | Howard-Melmore 138 kV | OH | Crawford | Active | AEP | 58 | 58 | 34.8 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-363 | + | Black Oak-Hatfield 500 kV | MD | Garrett | Active | APS | 300 | 300 | 220 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1363_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1363_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-363 | - | Black Oak-Hatfield 500 kV | MD | Garrett | Active | APS | 300 | 300 | 220 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1363_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-365 | + | Allen 345 kV | IN | Allen | Active | AEP | 200 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1365_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1365_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-365 | - | Allen 345 kV | IN | Allen | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1365_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-366 | + | Allen 345 kV | IN | Allen | Active | AEP | 250 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1366_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1366_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-366 | - | Allen 345 kV | IN | Allen | Active | AEP | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1366_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-368 | + | Tillman 138 kV | IN | Allen | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1368_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1368_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||
| AG1-368 | - | Tillman 138 kV | IN | Allen | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1368_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-369 | + | Logtown 138 kV | OH | Paulding | Active | AEP | 49.9 | 49.9 | 29.94 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1369_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1369_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-369 | - | Logtown 138 kV | OH | Paulding | Active | AEP | 49.9 | 49.9 | 29.94 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1369_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-373 | + | Nelson-Electric Junction 345 kV | IL | Lee | Active | ComEd | 100 | 0 | 10 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1373_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1373_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 11/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-373 | - | Nelson-Electric Junction 345 kV | IL | Lee | Active | ComEd | 100 | 0 | 10 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1373_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 11/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-377 | + | Philipsburg 115 kV | PA | Centre | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1377_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1377_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 8/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-377 | - | Philipsburg 115 kV | PA | Centre | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1377_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 8/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-378 | + | Philipsburg 115 kV | PA | Centre | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1378_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1378_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 8/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-378 | - | Philipsburg 115 kV | PA | Centre | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1378_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 8/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-382 | + | SGC Tap-Reese REC 46 kV | PA | Cambria | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1382_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1382_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-382 | - | SGC Tap-Reese REC 46 kV | PA | Cambria | Active | PENELEC | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1382_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-383 | + | Hickory 34.5 kV | VA | City of Chesapeake | Active | Dominion | 20 | 20 | 15.43 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1383_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1383_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-383 | - | Hickory 34.5 kV | VA | City of Chesapeake | Active | Dominion | 20 | 20 | 15.43 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1383_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1383_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-388 | + | Dunnsville 34.5 kV | Ex-Umphlette LLC | VA | Essex | Engineering and Procurement | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1388_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1388_imp.pdf | Document Posted | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ag1388_wmpa.pdf | https://www.pjm.com/pub/planning/project-queues/csa/ag1388_wmpa.pdf | Not Required | N/A | N/A | 9/30/2020 | N/A | N/A | 3/31/2023 | 3/31/2023 | N/A | N | No | |||||||||||
| AG1-388 | - | Dunnsville 34.5 kV | VA | Essex | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1388_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-392 | + | Gold 115 kV I | PA | Potter | Active | PENELEC | 40 | 40 | 24 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1392_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-392 | - | Gold 115 kV I | PA | Potter | Active | PENELEC | 40 | 40 | 24 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1392_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-393 | + | Fort Pickett DP 34.5 kV | VA | Dinwiddie | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1393_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1393_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-393 | - | Fort Pickett DP 34.5 kV | VA | Dinwiddie | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1393_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-394 | + | Boykins 34.5 kV | VA | Southampton | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1394_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1394_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-394 | - | Boykins 34.5 kV | VA | Southampton | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1394_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-398 | + | Brokaw-Lanesville 345 kV | IL | Fulton | Active | ComEd | 200 | 0 | 7.33 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1398_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1398_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/30/2021 | N/A | N | No | ||||||||||||||||||
| AG1-398 | - | Brokaw-Lanesville 345 kV | IL | Fulton | Active | ComEd | 200 | 0 | 7.33 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1398_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/30/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-403 | + | Blue Mound-Chestnut 345 kV | IL | McLean | Active | ComEd | 200 | 200 | 35.2 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1403_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/24/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-403 | - | Clinton-Brokaw 345 kV | IL | McLean | Active | ComEd | 200 | 200 | 35.2 | Capacity | Generation Interconnection | Wind | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/24/2024 | N/A | N | No | ||||||||||||||||||||||
| AG1-404 | + | Blue Mound-Chestnut 345 kV | IL | McLean | Active | ComEd | 100 | 100 | 100 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1404_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/24/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-404 | - | Clinton-Brokaw 345 kV | IL | McLean | Active | ComEd | 100 | 100 | 100 | Capacity | Generation Interconnection | Storage | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/24/2024 | N/A | N | No | ||||||||||||||||||||||
| AG1-405 | + | Walnut Grove-Asahi 69 kV | KY | McLean | Active | EKPC | 57 | 57 | 34.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1405_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1405_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||
| AG1-405 | - | Walnut Grove-Asahi 69 kV | KY | McLean | Active | EKPC | 57 | 57 | 34.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1405_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-406 | + | Walnut Grove-Asahi 69 kV | KY | McLean | Active | EKPC | 79 | 22 | 22 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1406_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1406_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||
| AG1-406 | - | Walnut Grove-Asahi 69 kV | KY | McLean | Active | EKPC | 79 | 22 | 22 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1406_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-410 | + | Maddox Creek-RP Mone 345 kV | OH | Van Wert | Active | AEP | 300 | 300 | 180 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1410_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1410_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||
| AG1-410 | - | Maddox Creek-RP Mone 345 kV | OH | Van Wert | Active | AEP | 300 | 300 | 180 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1410_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/25/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-412 | + | Ladysmith CT-Mine Road 230 kV | VA | Caroline | Active | Dominion | 200 | 200 | 80 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1412_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1412_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-412 | - | Ladysmith CT-Mine Road 230 kV | VA | Caroline | Active | Dominion | 200 | 200 | 80 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1412_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-415 | + | Double Toll Date-Old Chapel 138 kV | VA | Clarke | Active | APS | 50 | 50 | 25 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1415_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1415_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 1/2/2023 | N/A | N | No | ||||||||||||||||||
| AG1-415 | - | Double Toll Date-Old Chapel 138 kV | VA | Clarke | Active | APS | 50 | 50 | 25 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1415_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 1/2/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-416 | + | Sleepy Hollow 138 kV | WV | Jefferson | Active | APS | 125 | 125 | 91 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1416_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1416_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-416 | - | Sleepy Hollow 138 kV | WV | Jefferson | Active | APS | 125 | 125 | 91 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1416_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-417 | + | Gateway 69 kV | IN | Whitley | Active | AEP | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1417_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1417_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-417 | - | Gateway 69 kV | IN | Whitley | Active | AEP | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1417_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-418 | + | Gateway 69 kV | IN | Whitley | Active | AEP | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1418_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1418_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-418 | - | Gateway 69 kV | IN | Whitley | Active | AEP | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1418_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-419 | + | Lynnville-South Hamburg 69 kV | PA | Berks | Active | ME | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1419_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1419_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-419 | - | Lynnville-South Hamburg 69 kV | PA | Berks | Active | ME | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1419_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-420 | + | Campbell-Kiesters 138 kV | PA | Butler | Active | APS | 70 | 70 | 42 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1420_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1420_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-420 | - | Campbell-Kiesters 138 kV | PA | Butler | Active | APS | 70 | 70 | 42 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1420_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-421 | + | Lexington-Dooms 230 kV | VA | Augusta | Active | Dominion | 200 | 200 | 120 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1421_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1421_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-421 | - | Lexington-Dooms 230 kV | VA | Augusta | Active | Dominion | 200 | 200 | 120 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1421_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-422 | + | Lexington-Dooms 230 kV | VA | Augusta | Active | Dominion | 50 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1422_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1422_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-422 | - | Lexington-Dooms 230 kV | VA | Augusta | Active | Dominion | 50 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1422_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-424 | + | Sowers 138 kV | IN | Allen | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1424_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1424_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-424 | - | Sowers 138 kV | IN | Allen | Active | AEP | 100 | 100 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1424_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-436 | + | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 250 | 125 | 75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1436_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1436_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-436 | - | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 250 | 125 | 75 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1436_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-447 | + | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 305 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1447_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1447_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-447 | - | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 305 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1447_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-448 | + | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 360 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1448_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1448_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | |||||||||||||||||||
| AG1-448 | - | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | 360 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1448_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-450 | + | Airey-Vienna 69 kV II | MD | Dorchester | Active | DPL | 125 | 25 | 25 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1450_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | |||||||||||||||||||||
| AG1-450 | - | Airey-Vienna 69 kV II | MD | Dorchester | Active | DPL | 125 | 25 | 25 | Capacity | Generation Interconnection | Storage | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||||
| AG1-453 | + | Guardian 138 kV | IN | Noble | Active | AEP | 140 | 140 | 84 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1453_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1453_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-453 | - | Guardian 138 kV | IN | Noble | Active | AEP | 140 | 140 | 84 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1453_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-454 | + | Guardian 138 kV | IN | Noble | Active | AEP | 50 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1454_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1454_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-454 | - | Guardian 138 kV | IN | Noble | Active | AEP | 50 | 50 | 50 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1454_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-456 | + | Wildcat 138 kV | OH | Highland | Active | AEP | 180 | 30 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1456_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1456_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||
| AG1-456 | - | Wildcat 138 kV | OH | Highland | Active | AEP | 180 | 30 | 30 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1456_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-460 | + | Kincaid-Pana 345 kV | IL | Christian | Active | ComEd | 30 | 30 | 12 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1460_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1460_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-460 | - | Kincaid-Pana 345 kV | IL | Christian | Active | ComEd | 30 | 30 | 12 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1460_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-461 | + | Mumford 69 kV | DE | Sussex | Withdrawn | DPL | 30 | 30 | 19.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1461_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1461_imp.pdf | Document Posted | Withdrawn | N/A | N/A | 9/30/2020 | N/A | N/A | 9/20/2021 | 12/31/2023 | N/A | N | No | |||||||||||||||||
| AG1-461 | - | Mumford 69 kV | DE | Sussex | Active | DPL | 30 | 30 | 19.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1461_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-462 | + | Cordova B 345 kV | IL | Whiteside | Active | ComEd | 255 | 255 | 153 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1462_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-462 | - | Cordova B 345 kV | IL | Whiteside | Active | ComEd | 255 | 255 | 153 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1462_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-464 | + | Harrington 69 kV | DE | Kent | Active | DPL | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1464_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1464_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/17/2023 | N/A | N | No | ||||||||||||||||||
| AG1-464 | - | Harrington 69 kV | DE | Kent | Active | DPL | 50 | 50 | 20 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1464_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/17/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-465 | + | North Hanover-Gitts Run 115 kV | PA | York | Active | ME | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1465_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1465_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/5/2025 | N/A | N | No | ||||||||||||||||||
| AG1-465 | - | North Hanover-Gitts Run 115 kV | PA | York | Active | ME | 100 | 100 | 40 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1465_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/5/2025 | N/A | N | No | ||||||||||||||||||||
| AG1-466 | + | Orange 34.5 kV | VA | Orange | Active | Dominion | 14 | 14 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1466_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1466_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/19/2022 | N/A | N | No | ||||||||||||||||||
| AG1-466 | - | Orange 34.5 kV | VA | Orange | Active | Dominion | 14 | 14 | 8.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1466_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/19/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-467 | + | Somerset 34.5 kV | VA | Orange | Active | Dominion | 15.6 | 15.6 | 9.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1467_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1467_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/28/2022 | N/A | N | No | ||||||||||||||||||
| AG1-467 | - | Somerset 34.5 kV | VA | Orange | Active | Dominion | 15.6 | 15.6 | 9.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1467_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/28/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-469 | + | Gordonsville 34.5 kV | VA | Louisa | Active | Dominion | 15.6 | 15.6 | 9.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1469_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1469_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 11/11/2022 | N/A | N | No | ||||||||||||||||||
| AG1-469 | - | Gordonsville 34.5 kV | VA | Louisa | Active | Dominion | 15.6 | 15.6 | 9.36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1469_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 11/11/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-471 | + | Up Church-Wayne County 69 kV | KY | Wayne | Active | EKPC | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1471_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1471_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/2/2023 | N/A | N | No | ||||||||||||||||||
| AG1-471 | - | Up Church-Wayne County 69 kV | KY | Wayne | Active | EKPC | 60 | 60 | 36 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1471_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/2/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-476 | + | Mickelton 230 kV II | NJ | Gloucester | Active | AEC | 869 | 0 | 33.1 | Capacity | Generation Interconnection | Natural Gas; Other | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1476_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1476_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-476 | - | Mickelton 230 kV II | NJ | Gloucester | Active | AEC | 869 | 0 | 33.1 | Capacity | Generation Interconnection | Natural Gas; Other | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1476_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-478 | + | Wilmington 34.5 kV | IL | Will | Active | ComEd | 19.9 | 19.9 | 15.9 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1478_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1478_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||
| AG1-478 | - | Will County 34.5 kV | IL | Will | Active | ComEd | 19.9 | 19.9 | 15.9 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1478_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/29/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-481 | + | Warren 34.5 kV | PA | Warren | Withdrawn | PENELEC | 15.5 | 15.53 | 15.53 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1481_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1481_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 11/1/2021 | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-481 | - | Warren 34.5 kV | PA | Warren | Active | PENELEC | 15.5 | 15.53 | 15.53 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1481_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-483 | + | Dickerson 230 kV | MD | Montgomery | Active | PEPCO | 542.5 | 542.5 | 542.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1483_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1483_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-483 | - | Dickerson 230 kV | MD | Montgomery | Active | PEPCO | 542.5 | 542.5 | 542.5 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1483_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-484 | + | Mountain 115 kV | PA | Cumberland | Withdrawn | ME | 20 | 20 | 20 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1484_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1484_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 11/1/2021 | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-484 | - | Mountain 115 kV | PA | Cumberland | Active | ME | 20 | 20 | 20 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1484_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-485 | + | Brunot Island 138 kV | PA | Allegheny | Active | DL | 55 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1485_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1485_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-485 | - | Brunot Island 138 kV | PA | Allegheny | Active | DL | 55 | 55 | 55 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1485_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-486 | + | Orrtanna 115 kV | PA | Adams | Active | ME | 15 | 15 | 15 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1486_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1486_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-486 | - | Orrtanna 115 kV | PA | Adams | Active | ME | 15 | 15 | 15 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1486_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-487 | + | Gilbert 230 kV | NJ | Hunterdon | Active | JCPL | 20 | 20 | 20 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1487_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1487_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-487 | - | Gilbert 230 kV | NJ | Hunterdon | Active | JCPL | 20 | 20 | 20 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1487_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-489 | + | McClelland-Hoytdale 345 kV | PA | Lawrence | Active | ATSI | 175 | 175 | 145 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1489_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1489_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-489 | - | McClelland-Hoytdale 345 kV | PA | Lawrence | Active | ATSI | 175 | 175 | 145 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1489_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-490 | + | Shenango-McDowell 138 kV | PA | Mercer | Withdrawn | ATSI | 125 | 125 | 105 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1490_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1490_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/16/2021 | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-490 | - | Shenango-McDowell 138 kV | PA | Mercer | Active | ATSI | 125 | 125 | 105 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1490_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-492 | + | Kargle to Elizabethtown 69 kV | KY | Unknown | Active | EKPC | Energy | Merchant Transmission | Not Required | https://www.pjm.com/pub/planning/project-queues/arr-impact-studies/ag1492_arr-imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||
| AG1-492 | - | Kargle to Elizabethtown 69 kV | KY | Unknown | Active | EKPC | Energy | Merchant Transmission | Not Required | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||||
| AG1-493 | + | Blue Jacket to Blue Jacket Tap 69 kV | OH | Logan | Active | Dayton | Energy | Merchant Transmission | Not Required | https://www.pjm.com/pub/planning/project-queues/arr-impact-studies/ag1493_arr-imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||
| AG1-493 | - | Blue Jacket to Blue Jacket Tap 69 kV | OH | Logan | Active | Dayton | Energy | Merchant Transmission | Not Required | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/20/2020 | N/A | EE | No | |||||||||||||||||||||||||
| AG1-495 | + | Gilbert-Rocktown 34.5 kV | NJ | Hunterdon | Active | JCPL | 19.8 | 19.8 | 8.316 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1495_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1495_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||
| AG1-495 | - | Gilbert-Rocktown 34.5 kV | NJ | Hunterdon | Active | JCPL | 19.8 | 19.8 | 8.316 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1495_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/17/2021 | N/A | N | No | ||||||||||||||||||||
| AG1-497 | + | Cartanza 230 kV | DE | Kent | Active | DPL | 120 | 120 | 84 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1497_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1497_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||
| AG1-497 | - | Cartanza 230 kV | DE | Kent | Active | DPL | 120 | 120 | 84 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1497_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-499 | + | Lambs 12.47 kV | NJ | Gloucester | Active | AEC | 10 | 10 | 6 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1499_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1499_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/30/2020 | N/A | N | No | ||||||||||||||||||
| AG1-499 | - | Henry Harris 69 kV | NJ | Gloucester | Active | AEC | 12.6 | 12.6 | 7.56 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1499_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/30/2020 | N/A | N | No | |||||||||||||||||||||
| AG1-501 | + | Beaver 138 kV | OH | Lorain | Active | ATSI | 106.5 | 11.3 | 10 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1501_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1501_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-501 | - | Beaver 138 kV | OH | Lorain | Active | ATSI | 106.5 | 11.3 | 10 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1501_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-502 | + | Oak Green 115 kV | VA | Orange | Active | Dominion | 80 | 80 | 64 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1502_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-502 | - | Oak Green 115 kV | VA | Orange | Active | Dominion | 80 | 80 | 64 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-503 | + | Oak Green 115 kV | VA | Orange | Active | Dominion | 20 | 20 | 16 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1503_fea.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | |||||||||||||||||||||
| AG1-503 | - | Oak Green 115 kV | VA | Orange | Active | Dominion | 20 | 20 | 16 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/30/2023 | N/A | N | No | ||||||||||||||||||||||
| AG1-504 | + | Glenbrook-Salem 69 kV | PA | Luzerne | Withdrawn | PPL | 68 | 68 | 41.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1504_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1504_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 10/5/2021 | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-504 | - | Glenbrook-Salem 69 kV | PA | Luzerne | Active | PPL | 68 | 68 | 41.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1504_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-507 | + | Calumet 138 kV | IL | Cook | Active | ComEd | 296 | 296 | 296 | Capacity | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1507_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1507_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-507 | - | Calumet 138 kV | IL | Cook | Active | ComEd | 296 | 0 | 0 | Energy | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1507_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-508 | + | Independence 69 kV | VA | Grayson | Active | AEP | 63.3 | 63.3 | 9.3 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1508_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1508_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2025 | N/A | N | No | ||||||||||||||||||
| AG1-508 | - | Independence 69 kV | VA | Grayson | Active | AEP | 63.3 | 63.3 | 9.3 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1508_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2025 | N/A | N | No | ||||||||||||||||||||
| AG1-509 | + | Independence 69 kV | VA | Grayson | Active | AEP | 105.4 | 105.4 | 15.5 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1509_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1509_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2025 | N/A | N | No | ||||||||||||||||||
| AG1-509 | - | Independence 69 kV | VA | Grayson | Active | AEP | 105.4 | 105.4 | 15.5 | Capacity | Generation Interconnection | Wind | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1509_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 3/1/2025 | N/A | N | No | ||||||||||||||||||||
| AG1-510 | + | Kittatinny-Blairstown 34.5 kV | NJ | Warren | Active | JCPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1510_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1510_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-510 | - | Kittatinny-Blairstown 34.5 kV | NJ | Warren | Active | JCPL | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1510_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-511 | + | Kittatinny 230 kV | NJ | Warren | Active | JCPL | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1511_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1511_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-511 | - | Kittatinny 230 kV | NJ | Warren | Active | JCPL | 50 | 50 | 30 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1511_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-512 | + | University Park North 345 kV | IL | Will | Active | ComEd | 646 | 40 | 16 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1512_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1512_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-512 | - | University Park North 345 kV | IL | Will | Active | ComEd | 646 | 40 | 16 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1512_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-513 | + | Aurora 138 kV | IL | Will | Active | ComEd | 1026 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1513_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1513_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-513 | - | Aurora 138 kV | IL | Will | Active | ComEd | 1026 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1513_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-514 | + | Springdale CT III 138 kV | PA | Allegheny | Active | APS | 106 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1514_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1514_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-514 | - | Springdale CT III 138 kV | PA | Allegheny | Active | APS | 106 | 10 | 4 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1514_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-517 | + | Osage 138 kV | WV | Monongalia | Active | APS | 50 | 0 | 0 | Energy | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1517_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1517_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 4/1/2022 | N/A | N | No | ||||||||||||||||||
| AG1-517 | - | Osage 138 kV | WV | Monongalia | Active | APS | 50 | 0 | 0 | Energy | Generation Interconnection | Natural Gas | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1517_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 4/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-518 | + | Suffolk 230 kV | VA | City of Suffolk | Active | Dominion | 50 | 50 | 50 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1518_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1518_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-518 | - | Suffolk 230 kV | VA | City of Suffolk | Active | Dominion | 50 | 50 | 50 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1518_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 9/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-519 | + | Cash’s Corner 230 kV | VA | Louisa | Withdrawn | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1519_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1519_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/16/2021 | 10/28/2022 | N/A | N | No | ||||||||||||||||||
| AG1-519 | - | Cash’s Corner 230 kV | VA | Louisa | Active | Dominion | 20 | 20 | 12 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1519_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/28/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-520 | + | Hooversville-Rockingham 23 kV | PA | Somerset | Active | PENELEC | 4 | 4 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1520_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1520_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 1/1/2022 | N/A | Y | No | ||||||||||||||||||
| AG1-520 | - | Hooversville-Rockingham 23 kV | PA | Somerset | Active | PENELEC | 4 | 4 | 0 | Energy | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1520_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 1/1/2022 | N/A | Y | No | ||||||||||||||||||||
| AG1-527 | + | Imperial-Joffre 138 kV | PA | Allegheny | Active | APS | 215 | 215 | 129 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1527_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1527_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-527 | - | Imperial-Joffre 138 kV | PA | Allegheny | Active | APS | 215 | 215 | 129 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1527_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-528 | + | Tenmile 138 kV | WV | N/A | Active | AEP | 225 | 225 | 135 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1528_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1528_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-528 | - | Tenmile 138 kV | WV | N/A | Active | AEP | 225 | 225 | 135 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1528_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-529 | + | Farmview 138 kV | DE | Sussex | Active | DPL | 75 | 75 | 48.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1529_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1_529_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-529 | - | Farmview 138 kV | DE | Sussex | Active | DPL | 75 | 75 | 48.9 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1529_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-532 | + | Fields 34.5 kV | VA | Greensville | Active | Dominion | 13.5 | 13.5 | 8.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1532_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1532_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/12/2022 | N/A | N | No | ||||||||||||||||||
| AG1-532 | - | Fields 34.5 kV | VA | Greensville | Active | Dominion | 13.5 | 13.5 | 8.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1532_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/12/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-533 | + | Bartonsville-Meadowbrook 138 kV IV | VA | Frederick | Active | APS | 170 | 40 | 24 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1533_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1533_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||
| AG1-533 | - | Bartonsville-Meadowbrook 138 kV IV | VA | Frederick | Active | APS | 170 | 40 | 24 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1533_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/12/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-534 | + | Evergreen Mills 230 kV | VA | Loudoun | Active | Dominion | 200 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1534_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1534_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-534 | - | Evergreen Mills 230 kV | VA | Loudoun | Active | Dominion | 200 | 200 | 200 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1534_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-535 | + | State Line-S. Chicago Properties 138 kV | IL | Cook | Active | ComEd | 85 | 85 | 85 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1535_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1535_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||
| AG1-535 | - | State Line-S. Chicago Properties 138 kV | IL | Cook | Active | ComEd | 85 | 85 | 85 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1535_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-537 | + | Barterbrook-Stuarts Draft 115 kV | VA | Augusta | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1537_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1537_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-537 | - | Barterbrook-Stuarts Draft 115 kV | VA | Augusta | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1537_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-538 | + | Remington-Gordonsville 230 kV | VA | Culpeper | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1538_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1538_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-538 | - | Remington-Gordonsville 230 kV | VA | Culpeper | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1538_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-541 | + | St. Johns 115 kV | VA | Hanover | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1541_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1541_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-541 | - | St. Johns 115 kV | VA | Hanover | Active | Dominion | 75 | 75 | 32 | Capacity | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1541_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-545 | + | W. Quaker Rd-Disputanta 34.5 kV | VA | Prince George | Withdrawn | Dominion | 20 | 20 | 14 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1545_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1545_imp.pdf | Document Posted | N/A | N/A | 9/30/2020 | N/A | N/A | 9/17/2021 | 10/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-545 | - | W. Quaker Rd-Disputanta 34.5 kV | VA | Prince George | Active | Dominion | 20 | 20 | 14 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1545_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-551 | + | Parmele 12.5 kV | NC | Martin | Active | Dominion | 20 | 20 | 13.1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1551_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1551_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/15/2023 | N/A | N | No | ||||||||||||||||||
| AG1-551 | - | Parmele 12.5 kV | NC | Martin | Active | Dominion | 20 | 20 | 14 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1551_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/15/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-554 | + | South Kenton 138 kV | OH | Hardin | Active | AEP | 50 | 49.99 | 32.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1554_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1554_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||
| AG1-554 | - | South Kenton 138 kV | OH | Hardin | Active | AEP | 50 | 49.99 | 32.7 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1554_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||
| AG1-555 | + | Dequine 345 kV | IN | Tippecance | Active | AEP | 120 | 120 | 88.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1555_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1555_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||
| AG1-555 | - | Dequine 345 kV | IN | Tippecance | Active | AEP | 120 | 120 | 88.4 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1555_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-559 | + | Caroline Pines 22 kV | VA | Hanover | Active | Dominion | 20 | 20 | 13.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1559_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 10/21/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-559 | - | Caroline Pines 22 kV | VA | Hanover | Active | Dominion | 20 | 20 | 13.3 | Capacity | Generation Interconnection | Solar; Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1559_fea.pdf | Document Posted | Not Required | N/A | N/A | 9/30/2020 | N/A | N/A | 10/21/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-562 | + | Marysville-Gunn Road 345 kV | OH | Hardin | Active | AEP | 250 | 250 | 150 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1562_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1562_imp.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/4/2023 | N/A | N | No | ||||||||||||||||||
| AG1-562 | - | Marysville-Gunn Road 345 kV | OH | Hardin | Active | AEP | 250 | 250 | 150 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1562_fea.pdf | Document Posted | In Progress | N/A | N/A | 9/30/2020 | N/A | N/A | 12/4/2023 | N/A | N | No | ||||||||||||||||||||
| AG2-012 | + | Lardin 12 kV | PA | Fayette | Active | APS | 0.2 | 0.165 | 0 | Energy | Generation Interconnection | Solar | Not Required | Not Required | N/A | N/A | 10/14/2020 | N/A | N/A | 11/30/2020 | N/A | Y | No | |||||||||||||||||||||
| AG2-012 | - | Lardin 12 kV | PA | Fayette | Active | APS | 0.2 | 0.165 | 0 | Energy | Generation Interconnection | Solar | In Progress | N/A | N/A | 10/14/2020 | N/A | N/A | 11/30/2020 | N/A | Y | No | ||||||||||||||||||||||
| AG2-050 | + | Randle Cliff 13.8 kV | MD | Calvert | Active | BGE | 1 | 1 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag2050_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag2050_imp.pdf | Document Posted | Not Required | N/A | N/A | 11/25/2020 | N/A | N/A | 9/13/2021 | N/A | Y | No | ||||||||||||||||||
| AG2-050 | - | Randle Cliff 13.8 kV | MD | Calvert | Active | BGE | 1 | 1 | 0 | Energy | Generation Interconnection | Storage | In Progress | N/A | N/A | 11/25/2020 | N/A | N/A | 9/13/2021 | N/A | Y | No | ||||||||||||||||||||||
| AG2-052 5090276 | + | NIPS-PJM | N/A | N/A | Confirmed | Northern Indiana Public Service Company | 2 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ag2052_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 12/3/2020 | 2/1/2021 | 2/1/2026 | N/A | PP | No | |||||||||||||||||||||||||
| AG2-052 5090276 | - | NIPS-PJM | N/A | N/A | Active | Northern Indiana Public Service Company | 2 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/ag052_fea.pdf | Executed Agreement and/or Study | N/A | N/A | 12/3/2020 | 2/1/2021 | 2/1/2026 | N/A | PP | No | |||||||||||||||||||||||||
| AG2-109 | + | Fitchville-New London 69 kV | OH | Huron | Active | ATSI | 40 | 40 | 28.1 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 1/29/2021 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG2-109 | - | Hanville-Wellington 69 kV | OH | Huron | Active | ATSI | 40 | 40 | 28.1 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 1/29/2021 | N/A | N/A | 12/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG2-135 | + | Hoffman Estates 12.5 kV | OH | Pickaway | Active | Unknown | 0.3 | 0.28 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag2135_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag2135_imp.pdf | Document Posted | Not Required | N/A | N/A | 2/4/2021 | N/A | N/A | 7/30/2021 | N/A | Y | No | ||||||||||||||||||
| AG2-135 | - | Hoffman Estates 12.5 kV | OH | Pickaway | Active | ComEd | 0.3 | 0.28 | 0 | Energy | Generation Interconnection | Storage | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag2135_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ag2135_imp.pdf | Document Posted | Not Required | N/A | N/A | 2/4/2021 | N/A | N/A | 7/30/2021 | N/A | Y | No | ||||||||||||||||||
| AG2-138 | + | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | Energy | Merchant Transmission | Not Required | In Progress | N/A | N/A | 2/9/2021 | N/A | N/A | 2/8/2021 | N/A | EE | No | |||||||||||||||||||||||||
| AG2-138 | - | Olive-University Park 345 kV | IN | LaPorte | Active | AEP | Energy | Merchant Transmission | Not Required | N/A | N/A | 2/9/2021 | N/A | N/A | 2/8/2021 | N/A | EE | No | ||||||||||||||||||||||||||
| AG2-205 | + | Bonney Forge 23 kV | N/A | N/A | Active | PENELEC | Energy | Generation Interconnection | Not Required | Not Required | N/A | N/A | 3/5/2021 | N/A | N/A | 5/1/2023 | N/A | Y | No | |||||||||||||||||||||||||
| AG2-205 | - | Bonney Forge 23 kV | N/A | N/A | Active | PENELEC | Energy | Generation Interconnection | In Progress | N/A | N/A | 3/5/2021 | N/A | N/A | 5/1/2023 | N/A | Y | No |